GST reimbursement for post-GST works contracts requires assessment under the notification's applicable provision, not the pre-GST clause.
Case-Laws
GST
GST reimbursement under the contractual tax-transition notification must be assessed under paragraph 4 for post-GST contracts and ongoing projects with estimates approved before 1 July 2017, applying GST rates. Paragraph 3(iv), confined to pre-GST contracts, cannot govern or defeat claims concerning contracts executed after that date. The reimbursement claim requires reconsideration under paragraph 4 following a personal hearing and a reasoned decision; coercive action remains restrained pending that determination.
TMI Updates – Highlights, quick notes, marquee, annotation, news, alerts
= = = = = = = =
Plain text (Extract) only
For full text:-Visit the Source
= = = = = = = =