Project Delay Penalty Quashed: Court Sides with Firm for Timely Production Commencement.

Case-Laws – GST – Highlights – The petitioner was directed to pay a 5% penalty of the prevailing plot cost for the belated implementation of the project as per Clause 2.1.2.(a) of O.O.No.30 of 2020. However, the petitioner complied with the clause by uti

Project Delay Penalty Quashed: Court Sides with Firm for Timely Production Commencement.
Case-Laws
GST
The petitioner was directed to pay a 5% penalty of the prevailing plot cost for the belated implementation of the project as per Clause 2.1.2.(a) of O.O.No.30 of 2020. However, the petitioner complied with the clause by utilizing more than 65% of the plot and had commenced production before dispatching goods. Despite paying the penalty amount, the petitioner was again directed to pay a

= = = = = = = =