Profiteering allegations dismissed for post-GST real estate project charging 8% GST + ITC.
Case-Laws
GST
The respondent commenced a real estate project “Swastik Heights” in the post-GST regime, with commencement certificate issued on 08.03.2018 and GST registration effective from 27.02.2018. Initially, GST was charged at 8% with input tax credit (ITC). From 01.04.2019, the respondent had the option to charge either 8% GST with ITC or 1% without ITC, but continued charging 8% with ITC. T
= = = = = = = =
Plain text (Extract) only
For full text:-Visit the Source
= = = = = = = =