HM LOGISTIC SOLUTIONS Versus UNION OF INDIA

2018 (11) TMI 142 – GUJARAT HIGH COURT – TMI – Detention of goods alongwith vehicle – detention on the ground that E-Way bill was not updated – Held that:- By way of ad interim relief, it is provided that the respondent shall release truck along with goods upon the petitioner furnishing bank guarantee for the said sum of ₹ 6,17,760/ Notice returnable on 01.11.2018. – R/SPECIAL CIVIL APPLICATION NO. 16571 of 2018 Dated:- 25-10-2018 – MR AKIL KURESHI AND MR UMESH TRIVEDI, JJ. For The Petitioner : KUNTAL A PARIKH (7757) For The Respondent : MR PRANAV TRIVEDI, AGP (99) ORAL ORDER (PER : HONOURABLE MR.JUSTICE AKIL KURESHI) 1. Draft amendment is allowed. 2. Petitioner is a transporter. The goods being transported by the petitioner have be

= = = = = = = =