Specification of Proper Officer under various provisions of DGST Act, 2017.

Specification of Proper Officer under various provisions of DGST Act, 2017.
F.IV/Misc/HR/GST/27/2015-16/Part file/5239 -5245 Dated:- 9-5-2018 Delhi SGST
GST – States
GOVERNMENT OF NATIONAL CAPITALTERRITORY OF DELHI
DEPARTMENT OF TRADEAND TAXES
(HUMAN RESOURCE BRANCH)
VYAPAR BHAWAN, I.P. ESTATE, NEW DELHI-110002.
ORDER
F.NO. F.IV/Misc/HR/GST/27/2015-16/Part file/5239 -5245
Dated: 09.05.2018
Specification of Proper Officer under various provisions of DGST Act, 2017.
In exercise

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

M/s. Arjan Dass Steel Castings Pvt. Ltd. Versus Commissioner of CGST & Central Excise, Kolkata-II

M/s. Arjan Dass Steel Castings Pvt. Ltd. Versus Commissioner of CGST & Central Excise, Kolkata-II
Central Excise
2018 (7) TMI 161 – CESTAT KOLKATA – TMI
CESTAT KOLKATA – AT
Dated:- 9-5-2018
Appeal No. E/76850/2017 – FO/76049/2018
Central Excise
Shri P.K. Choudhary, Member (Judicial)
Shri N.K. Choudhary, Advocate for the for the Appellant/Applicant (s)
Shri H.S. Abedin, AC(AR) Respondent (s)
ORDER
Per Shri P.K.Choudhary
1. Briefly stated the facts of the case are that the appellant is engaged in the manufacture of M.S. Ingots falling under chapter 72 of the Central Excise Tariff Act, 1985. On 08.11.2006, the officers of the department carried out stock verification at the factory premise of the appellant and found that there was a shortage of 31.705 MT of finished goods of non-alloy steel ingots. The officers recorded the statements of one Shri Subal Bera, authorised signatory and Shri Sandip Agarwal, Director who had accepted the shortage. But could not expl

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

of pipings/risings formed on the edges of the ingots. Such layers of pipings/risings were removed later after the finished goods had been weighed, and it was due to the removal of such extra layers of piping/ risings that there was an apparent difference between the weight recorded in the register and the weight of the actual stock. He further submitted that Shri Sandip Agarwal was not involved in the day to day functioning of the factory and therefore, his statement should not be relied upon. He also stated that the appellant had submitted a certificate from the Chartered Engineer according to which they were eligible for taking credit of Rs. 4,24,573.62. He further submitted that all payments made during the investigation were made under protest. There was no intention to evade payment of duty by suppressing facts. He relied upon the judgment of the Hon'ble Gujarat High Court in the case of Mundra Ports & Special Economic Zone Ltd. v. CCE & Cus reported as 2015 (39) STR 726 (Guj.).

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Court has referred to the 'user test' outlined in the case of CCE, Coimbatore v. Jawahar Mills Ltd. reported as 2001 (132) ELT 3 (SC), which lays down the ratio in determining whether particular goods could be categorised as capital goods or not.
7. Regarding the shortage of finished goods detected during the stock verification, I do not find any force in the submission of the ld. Advocate, as it was not substantiated by any evidence. The demand of duty is required to be upheld. I find that in order to impose penalty under section 11AC of the Central Excise Act, it is necessary to prove that there was fraud, collusion, wilful misstatement, suppression of facts with intent to evade payment of duty on the part of the appellant. There is no material available on record of clandestine removal of goods of the shortage quantity.
8. Accordingly, I uphold the demand of Central Excise Duty of Rs. 82,906/- as per Section 11A of the Central Excise Act, which has already been paid by the Appella

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

In Re : M & I Materials India Private Limited

In Re : M & I Materials India Private Limited
GST
2018 (7) TMI 1493 – AUTHORITY FOR ADVANCE RULING – MAHARASHTRA – 2018 (15) G. S. T. L. 423 (A. A. R. – GST)
AUTHORITY FOR ADVANCE RULING – MAHARASHTRA – AAR
Dated:- 9-5-2018
No. GST-ARA-23/2017-18/B-31
GST
B.V. Borhade (Member) and Pankaj Kumar (Member)
PROCEEDINGS
(under section 98 of the Central Goods and Services Tax Act, 2017 and the Maharashtra Goods and Services Tax Act, 2017)
The present application has been filed under section 97 of the Central Goods and Services Tax Act, 2017 and the Maharashtra Goods and Services Tax Act, 2017 [hereinafter referred to as “the CGST Act and MGST Act”] by M&I MATERIALS INDIA PRIVATE LIMITED, the applicant, seeking an advance ruling in respect of the applicability of GST on:
What is the correct Harmonized System of Nomenclature (HSN) code and the applicable GST rate for our products MIDEL eN 1204 (rapeseed oil based dielectric transformer fluid) and MIDEL eN 1275 (soya oi

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Ltd. based in UK (hereinafter referred to as 'M&I UK').
2. The company commenced its operations in the month of April 2014 and is, inter alia. engaged in the following activities:
2.1 Import of 'Midel Dielectric Fluids' from M&l UK and subsequent sale in India
2.2 Establishing local warehousing and distribution capability.
2.3 Marketing and business development activity with a focus on assisting in the development of the Midel Dielectric Fluids business in India
2.4 Provide local first line support for any technical queries.
3.  The details of the products for which the Advance Ruling is being sought is as follows:
3.1 MIDEL eN 1204
3.1.1 It is a vegetable oil based dielectric transformer fluid It is a chemically modified rapeseed oil based natural ester
3.1.2 It is used as electric insulator in transformers Its function is to provide electrical insulation, suppress corona and arcing, and to serve as a coolant.
3.1.3 We have classified MIDEL eN 1204 as pe

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

It is used as electric insulator in transformers. Its function is to provide electrical insulation, suppress corona and arcing, and to serve as a coolant.
3.2.3 We have classified MIDEL eN 1215 as per HSN code under the First Schedule of the Customs Tariff Act, 1975 under the entry 15180039.
3.2.4 The applicable Indian Standards (IS) of the Bureau of Indian Standards (BIS) under the Bureau of Indian Standards Act, 1986 is IS 16659:2017.
4. The rate of GST applicable on supply of various goods is notified vide Notification No. 1/2017-Central Tax (Rate) dated 28 June 2017, as amended from time to time (hereinafter referred to as “the Notification”).
4.1 Under the Notification, the HSN code 1518 appears under “Schedule I – 2.5%” as well as “Schedule 2 – 6%”. The relevant extract is reproduced hereunder for ease of reference:
4.2
S. No.
Chapter / Heading / Sub-heading / Tariff item
Description of goods
Schedule I – 2.5%
90.
1518
Vegetable fats and oils and their fractions, boil

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

classification for both of our above mentioned products
Statement containing the applicant's interpretation of law and/or facts, as the case may be, in respect of the aforesaid question(s) (i.e. applicant's view point and submissions on issues on which the advance ruling is sought)
We submit that both our products viz. MIDEL eN 1204 and MIDEL eN 1215, are chemically modified vegetable oil based transformer fluids which should be classified under Entry at S. No. 90 of Schedule – 1 [applicable rate of Central Goods and Services Tax (CGST) – 2,5%]. To support our view, we would like to put forth our contentions, without prejudice to each other, as follows:
1. Specific entry should prevail over general entry
1.1 Chemically modified vegetable oils are more specifically covered under Entry at S No 90 of Schedule – I of the Notification. Hence, both our products viz, MIDEL eN 1204 and MIDEL eN 1215 should be classified under the said entry.
1.2 Further, explanations (iii) and (iv

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

description shall be preferred to headings providing a more general description. However, when two or more headings each refer to part only of the materials or substances contained in mixed or composite goods or to part only of the items in a set put up for retail sale, those headings are to be regarded as equally specific in relation to those goods, even If one of them gives a more complete or precise description of the goods
(emphasis supplied)
1.4 The entry at S. No 27 of Schedule II – 6% is a general entry mainly referring to animal fats and oils while vegetable fats and oils are mentioned only cursorily. Further, it should be noted under the said entry only those vegetable fats or oils can be covered which are not specified elsewhere.
1.5 It is a well established principle of taxation jurisprudence for resolving classification disputes that a specific entry shall prevail over a general entry. In this regard, we would like to bring to your attention the judgement of the Hon&#39

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

e general Entry 18 which relates to rayon and synthetic fibres and yarn i.e. manmade fibres.”
1.7 Given the above, we submit that a combined reading of relevant entries along with the general rules of interpretation [supra] and the decisions of the Apex Court on the matter, it is evidently clear that both our products should fall under Schedule I – 2.5% as it provides a more specific description applicable to both our products
2. Intention of the legislature
2 .1 It is pertinent to note that whereas under the Customs law, animal or vegetable fats and oils are part of the same entry i.e. 1518.00 (supra), under the GST regime a conscious decision has been made by the GST Council to split the said entry between vegetable fats and oils and animal fats and oil by including vegetable fats and oil under Schedule I of the Notification which provides for lower GST rate of 2.5%.
2.2 The Constitution Bench of the Hon'ble Supreme Court of India in Dattatraya Govind Mahajan versus State of

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

e above, if it is assumed that either or both of our products cannot be classified under entry at S. No. 90 of Schedule I – 2.5%, we would like to submit that, entry at S. No. 88 of Schedule I – 2.5% also provides an appropriate description of our products, and that in no case the said products can be classified under the general entry at S. No. 27 of Schedule II – 6%.
3.2 In this regard, we would like to reproduce the entry at S. No 88 of Schedule 1 – 2 5% for ease of reference:
S. No.
Chapter / Heading / Subheading / Tariff item
Description of goods
Schedule I – 2.5%
88.
1516
Vegetable fats and oils and their fractions, partly or wholly hydrogenated, inter-esterified, re-esterified or elaidnised, whether or not refined, but not further prepared. ”
3.3 Both our products being vegetable oil based esterified transformer fluids, we submit that they should fall within the ambit of the said entry and classified accordingly.
4. Beneficial rate under the Maharashtra Value Added Tax

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

rdingly, we submit that, both our products should fall within the ambit of entry at S. No 90 of Schedule I – 2.5%.
Prayer
1. In light of the above, we pray that both our products viz. MIDEL eN 1204 and MIDEL eN 1215 be classified under Entry at S. No. 90 of Schedule – I i.e. at the applicable rate of CGST of 2.5%.
2. We crave leave to add, to alter, amend and/or modify all or any of the foregoing submissions
3. We pray that a hearing be granted to us before any decision is taken in this matter and also crave leave to produce documents / records / case law at the hearing granted to us.”
Additional submission dt.16.03.2018
We, M/s. SKP Business Consulting LLP, in our capacity as authorised representatives of M/s. M&I Materials India Private Limited (hereinafter referred to as “the Company” or “us” or “we”) refer to the preliminary hearing held for admission / rejection of our advance ruling application on 7 March 2018 We thank you for admitting our application and granting us anoth

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ost of the customers of our products include government and non-government entities operating in the essential sector of electricity generation, transmission and distribution.
1.3 Similarly, the Tamil Nadu government vide Notification-III. G O Ms. No. 77, No II(1)/CTR/12(R-I7)/2011 dated 11 July 2011 had reduced the tax payable by any dealer to 5% on the sale of any goods except petrol, diesel and cement to certain entities engaged in generation, transmission and distribution of electrical energy.
1.4 Given the above, it is evident that our products being supplied to an essential sector, the incidence of tax was kept at a minimum i.e. 5%, to avoid any undue tax burden on the ultimate customers of essential sector of electricity.
1.5 At this juncture we would like to reproduce the relevant extract from the minutes of the 3rd and the 4th GST Council meetings held on 18-19 October 2016 and 3-4 November 2016 respectively, wherein the principles for fixation of GST rates were debated upo

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ing combined tax rate of Central Excise and VAT between 15% and less than 21 %):
iv. 26 % (to cover those goods presently attracting combined tax rates of Central Excise and VAT equal to or more than 21 %)”
[emphasis supplied]
– 4th GST Council meeting
“10. Initiating the discussion, the Secretary to the Council briefly recapitulated the discussion on this issue in the 3rd GST Council Meeting on 18-19 October, 2016. He recapitulated the proposal to have a four rate GST structure and the rates could be 6%, 12%, 18% and 26%. He explained that a slab of 6% was needed for such goods where VA T was being charged at 5% and Central Excise duty on the same goods was Nil. He stated that if such goods put in the 12% rate band, it would adversely affect the poorer sections of the society.”
[emphasis supplied]
1.6 Applying the principles emanating from the discussions and observations made by the GST Council it is incontrovertible that our products should be classified under the GST rate bra

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

cted to beneficial rates of tax under the erstwhile law.
1.10 We submit that the above discussion supplies further credence to our earlier submissions that our products viz. MIDEL eN 1204 and MIDEL eN 1215 being products consumed by entities operating in the essential sector of electricity generation, transmission and distribution, and being subjected to beneficial rate of tax under the erstwhile indirect tax regime, should be classified under Entry at S. No. 90 of Schedule -I of the Notification No. 1/2017-Central Tax (Rate) dated 28 June 2017, as amended from time to time, i.e chargeable to GST at the rate of 5%.
2. Non-classification as 'mixtures'
2.1 The quantity of additives in our products viz. MIDEL eN 1204 and MIDEL eN 1215 is minimal i.e. 0.3% of the total weight of the product. Therefore, the said products cannot be considered as 'mixtures' covered under Entry at S. No. 27 of Schedule II – 6%.
2.2 In order to corroborate our explanation, a copy of test rep

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

fluid. The dealer is in his application admit that use of the product is transformer fluid, which means it is inedible and hence covered by Schedule II. Chapter heading 1518 and rate of tax applicable is 6%.
(ii) MIDEL eN 1204- In this sheet product use is mentioned as dielectric fluid. It is blend of natural triglyceride esters (vegetable oil). It clearly shows that the product is intended to be used as only dielectric fluid. The dealer is in his application admit that use of the product is transformer fluid, which means it is inedible and hence covered by Schedule II. Chapter heading 1518 and rate of tax applicable is 6%.
2) The above submission is made in the light of Notification No. 1/2017-State Tax(Rate) No. MGST-1017/C.R. 104/Taxation 1 dated 29/06/2017.
Hon. Forum is humbly requested to admit the application for Advance Ruling and decide the issue as per above mentioned notification. ”
04. HEARING
The case was taken up for hearing on dt.07.03.2018 when Sh. Jigar Doshi, Sh

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

under Schedule II and not under Schedule I as claimed by the applicant.
05. OBSERVATIONS
We have gone through the facts of the case. We have been called upon to decide the classification of the products MIDEL eN 1204 (rapeseed oil based dielectric transformer fluid) and MIDEL eN 1215 (soya oil based dielectric transformer fluid). Before we ascertain the applicability of the schedule entries, at the cost of repetition, let us have a look at the information about the products as provided by the applicant-
MIDL eN1204
It is a vegetable oil based dielectric transformer fluid. it is chemically modified rapeseed oil based natural ester.
It is used as electric insulator in transformers. Its function is to provide electrical insulation, suppress corona and arcing, and to serve as a coolant.
The applicable Indian Standards (IS) of the Bureau of Indian Standards (BIS) under the Bureau of Indian Standards Act, 1986 is IS 16659:2017.
MIDEL eN 1215
It is a vegetable oil based dielectric tr

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

nal officer had pointed to a document called 'Safety Data Sheet', the relevant parameters from which can be seen below :
Particulars
MIDEL eN 1204 (rapeseed oil based dielectric transformer fluid)
MIDEL eN 1215 (soya based dielectric transformer fluid).
1. Identification of the Substance/Mixture and of the Company/Undertaking
1.1 Product Identifier Material Name: MIDEI. eN 1204.
1.2 Relevant identified uses of the substance or mixture and uses advised against Product Use: Dielectric fluid
Uses advised against: None. 1.3 Details of the supplier of the substance or mixture
Company: M&I Materials Ltd. Hibernia Way, Trafford Park, Manchester, M32 0ZD, UK.
1.1 Product Identifier Material Name: MIDEL eN 1215.
1.2 Relevant identified uses of the substance or mixture and uses advised against Product Use: Dielectric fluid
Uses advised against: None 1.3 Details of the supplier of the substance or mixture
Company: M&I Materials Ltd., Hibernia Way, Trafford Park, Manchester. M3

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

56-68-3 Description: Blend of natural triglyceride esters (vegetable oil)
Composition:
Constituent CAS Number Contents Blend of natural triglyceride esters 68956-68-3 >98.5% Performance enhancing additives Proprietary<1.5% All constituents are listed on the TSCA inventory. Additives used in this product are a trade secret, but do not lead to classification of the substance as hazardous. 3 Substance CAS No.: 68956-68-3 Description: Blend of natural triglyceride esters (vegetable oil) Composition: Constituent CAS Number Contents Blend of natural triglyceride esters 68956-68-3 >98.5% Performance enhancing additives Proprietary<1.5% All constituents are listed on the TSCA inventory. Additives used in this product are a trade secret, but do not lead to classification of the substance as hazardous. 4. First Aid Measures 4,1 Description of first aid measures Inhalation: None envisaged due to the low vapour pressure of the substance Skin: Wash with soap and water. Obtain medical a

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

handling Avoid eye and prolonged skin contact
7.2 Conditions for safe storage, including any incompatibilities No special precautions required
7.3 Specific end use(s)
Exposure to air should be minimised. Opened containers should be properly resealed
7.1 Precautions for safe handling Avoid eye and prolonged skin contact
7.2 Conditions for safe storage, including any incompatibilities No special precautions required
7.3 Specific end use(s)
Exposure to air should be minimised. Opened containers should be properly resealed
8. Exposure Controls/ Personal Protection
8 1 Control parameters No relevant control parameters.
8 2 Exposure controls
Eye washes should be available for emergency use
Respiratory protection: None required.
Skin protection: Wear coveralls Hand protection: Wash hands after use. For prolonged or repeated skin contact gloves are recommended
Eye protection If splashes are likely to occur wear safety glasses.
8.1 Control parameters No relevant control paramete

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ising
Aspiration hazard: Not considered an aspiration hazard Carcinogenicity/mutagenicity: Not considered a mutagenic hazard or carcinogen. This product is not considered to be a carcinogen by IARC, ACGIH, NTP or OSHA.
11.1 Information on toxicological effects Likely routes of exposure: Skin and eyes are the most likely routes for exposure Accidental ingestion may occur. Inhalation is not expected to be a relevant route of exposure. Product is vegetable oil based and as such non-toxic.
Acute oral toxicity: Considered to be low toxicity, vegetable oil.
Acute dermal toxicity: Considered to be low toxicity. Acute inhalation toxicity: Low volatility makes inhalation unlikely
Skin corrosion/irritation: Considered to be not irritating Eye corrosion/irritation Considered to be not irritating. Respiratory or skin sensitisation: Considered to be not sensitising
Aspiration hazard: Not considered an aspiration hazard Carcinogenicity/mutagenicity: Not considered a mutagenic hazard or carcino

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

inct identity as being a “transformer fluid”. They are also given distinct names to establish their identity.
* We only learn that the impugned products are vegetable oil based.
* Neither the exact ingredients nor the exact additives, and the composition of each of these are available before us.
* The information shows that the products are a blend of natural triglyceride esters. They also contain additives.
* The applicant has argued that the quantity of additives in their products is minimal i.e. 0.3% of the total weight of the product. Therefore, the said products cannot be considered as 'mixtures'.
Having seen thus, we look at the contention with regard to the applicability of the schedule entries thus –
* If it is assumed that either or our products cannot be classified under entry at S. No. 90 of Schedule I – 2.5%, we would like to submit that, entry at S. No. 88 of Schedule I – 2.5% also provides an appropriate description of our products, and that in no case

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ble mixtures or preparations of animal or vegetable fats or oils or of fractions of different fats or oils of this chapter, not elsewhere specified of included
12% [6 + 6]
A look at the description as found in the entries and the product information, as reproduced above, we are constrained to observe thus –
1. The products are not vegetable fats and vegetable oils per se.
2. The products do not remain mere vegetable fat or mere vegetable oil. The impugned products are a distinct product which is known in the market as a dielectric transformer fluid.
3. The applicant has argued that the products cannot be considered as 'mixtures'. However, we find a reference to the products being a 'substance' or 'mixture' in the Safety Data Sheet of these products as can be seen thus –
1.3 Details of the supplier of the substance or mixture
4.  No information about the manufacturing process has been given. Neither any information has been shared as to the ingredient

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

, BLOWN, POLYMERISED BY HEAT IN VACUUM OR IN INERT GAS OR OTHERWISE CHEMICALLY MODIFIED, EXCLUDING THOSE OF HEADING 1516 ; INEDIBLE MIXTURES OR PREPARATIONS OF ANIMAI. OR VEGETABLE FATS OR OILS OR OF FRACTIONS OF DIFFERENT FATS OR OILS OF THIS CHAPTER, NOT ELSEWHERE SPECIFIED OR INCLUDED
1518 00
–
Animal or vegetable fats and oils and their fractions, boiled, oxidized, dehydrated, sulphurised, blown, polymerized by heat in vacuum or in inert gas or otherwise chemically modified, excluding those of heading 1516; inedible mixtures or preparations of animal or vegetable fats or oils or of fractions of different fats or oils of this Chapter, not elsewhere specified or included :
 

Lin seed oil:
1518 00 11

Edible grade
151800 19

Other
 

Castor oil, dehydrated:
1518 0021

Edible grade
1518 00 29

Other
 

Other Vegetable oil and its fats:
1518 00 31

Edible grade
1518 00 39

Other
151800 40

Other
From the Tariff Heading 1518 as reproduced

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

otes (HSN) in respect of the part 1 (as reproduced above) of Heading 1518 says-
“This part covers animal or vegetable fats and oils and their fractions which have been subjected to processes which modify their chemical structure thereby improving their viscosity, drying power (i.e., the property of absorbing oxygen when exposed to the air and forming elastic films) or modifying their other properties, provided they retain their original fundamental structure and are not more specifically covered elsewhere, e.g.:
Thus, the Notes make it clear that the animal or vegetable fats and oils and their fractions should retain their original fundamental structure.
e. The part 1 (as reproduced above) of Heading 1518 speaks of certain processes which have been subjected to vegetable and animal oils. But the HSN Notes say that despite undergoing these processes, the vegetable or animal oils should retain their original fundamental structure. In the present case, we have a final product which is

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

products as dielectric transformer fluid. The products are described as a “fluid”. Is a fluid same as an oil? A fluid is different from even a liquid, let alone oil. The products are not being sold as a modified vegetable oil but as products which result from the adaptation of the natural triglyceride esters to obtain a dielectric transformer fluid. In view thereof, we are convinced that the impugned products would not be covered by the part 1 (as reproduced above) of Hearting 1518. The same reasoning would apply to non-applicability of entry 88 of Schedule I.
f. We now come to part 2 (as reproduced above) of Heading 1518. This part covers inedible mixtures or preparations of animal or vegetable fats or oils or of fractions of different fats or oils of the Chapter 15. The present products, as discussed above, are a preparation from natural triglyceride esters. They are based or derived from “rapeseed oil based” or “soya based”. In addition, the products are inedible. And even though t

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

affect our decision. We find that there is Chapter 38 of the Customs Tariff which covers residual products of the chemical or allied industries. However as the exact composition of the product is not revealed to us by the applicant and therefore on the basis of the facts at hand, we find them insufficient to arrive at any decision as to the classification of the product under Chapter 38 and accordingly, taking into consideration only the details revealed to us, we find that the product is classifiable under Chapter 15 of the Customs Tariff Heading/GST Tariff.
6. We are not in doubts that entry 88 and 90 of Schedule I of the Notification No. 1/2017-Central / State Tax (Rate) would not cover the impugned products. We are also convinced that the impugned products are not covered by any entry of the Schedule in the Notification No. 2/2017- Central / State Tax (Rate) for goods exempted from GST. It is only the question of entry 90 or any other entry of the Notification No. 1/2017- Central

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

M/s S.A.I.L. Versus Commr. of CGST, C. Excise, Ranchi

M/s S.A.I.L. Versus Commr. of CGST, C. Excise, Ranchi
Central Excise
2018 (12) TMI 714 – CESTAT KOLKATA – TMI
CESTAT KOLKATA – AT
Dated:- 9-5-2018
Ex. Appeal No.75352/18 – FO/76542/2018
Central Excise
SHRI P. K. CHOUDHARY, JUDICIAL MEMBER
Shri S. P. Majumdar, Adv. for the Appellant (s)
Shri S. Mukhopadhyay, Supdt. (A.R.) for the Revenue
ORDER
Per Shri P. K. Choudhary:
This is an appeal filed by the Appellant against the Order-in- Appeal No.157/RAN/2017 dated 31.10.2017 passed by Commr. of CGST & Central Excise (Appeals-I), Ranchi.
2. Briefly stated the facts of the case are that the appellant, M/s Steel Authority of India Ltd. (SAIL), Bokaro Steel Plant, is engaged in the manufacture of various articles of iro

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ds.
4. I find that Rule 3(5A) of Cenvat Credit Rules, 2004, prescribes that “if the capital goods are cleared as waste and scrap, the manufacturer shall pay an amount equal to the duty leviable on the transaction value”. I also find from the record that the appellant all along stated that waste and scrap generated from the capital goods were brought into the factory much before 01.04.1994, when where was no provisions for availing credit on the capital goods. It is the case of the appellant that since there is no provision for availing credit on the capital goods, no Excise duty was required to be paid. I find that the Adjudicating Authority has also dropped the demand attributable to rejected machinery/machinery spares/equipments, which w

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

M/s Dynamic Commodities Pvt. Ltd. Versus Commr. of CGST, C. Excise, Kolkata North

M/s Dynamic Commodities Pvt. Ltd. Versus Commr. of CGST, C. Excise, Kolkata North
Service Tax
2018 (12) TMI 727 – CESTAT KOLKATA – TMI
CESTAT KOLKATA – AT
Dated:- 9-5-2018
S.T. Appeal No.75423/18 – FO/76543/2018
Service Tax
SHRI P. K. CHOUDHARY, JUDICIAL MEMBER
Shri Sushil Kr. Goyal, C.A. for the Appellant (s)
Shri A. Roy, Supdt. (A.R.) for the Revenue
ORDER
Per Shri P. K. Choudhary :
This is an appeal filed by the Appellant against the Order-in- Appeal No.189/ST-I/KOL/2017 dated 17.08.2017 passed by Commr. of CGST & Central Excise (Appeals-I), Kolkata.
2. Briefly stated the facts of the case are that the appellant is a provider of “Forwarding Contract Service” and Maintenance or Repair Service”. A show-cause

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

s submission that the complete facts and figures were duly disclosed in the ST-3 Returns and proper records as required were being maintained by the appellant and therefore, there cannot be any allegation of suppression against the appellant and the extended period of limitation of five years is not invokable. The ld.C.A.for the appellant also submits that the demand is barred by limitation.
4. The ld.A.R. for the Revenue, reiterated the findings of the lower authorities.
5. Heard both sides and perused the appeal records.
6. On perusal of records, I find that Rule 4 (7) of the Cenvat Credit Rules, 2004, states that “the Cenvat Credit in respect of input service shall be allowed, on or after the day that which payment is made of the valu

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

tax has been paid subject to realization of that cheque.”
The above Rule specifies that the date of payment in case of service tax shall be the date of presentation of cheque subject to realization of cheque. I also find from the records that none of the cheque issued by the appellant were dishonoured. I also observed that the issue is covered by the decision of the Co-ordinate Bench of the Tribunal in the case of India Cement Limited Vs. Commr. of Central Excise, Hyderabad : 2002 (150) ELT 1344. In this regard, the relevant Para is reproduced below:
“8. We have carefully considered the submissions made by both sides. In the instant case, the penalties have been imposed on the appellants on the ground that there is a gap of few days bet

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Aurobindo Pharma Ltd., Unit XII Versus Commissioner of Central Tax, Central Excise & Service Tax – GST

Aurobindo Pharma Ltd., Unit XII Versus Commissioner of Central Tax, Central Excise & Service Tax – GST
Central Excise
2018 (5) TMI 1805 – CESTAT HYDERABAD – TMI
CESTAT HYDERABAD – AT
Dated:- 9-5-2018
Appeal No. E/31214/2017 – A/30583/2018
Central Excise
Mr. M.V. RAVINDRAN, MEMBER (JUDICIAL)
Shri N Ram Reddy, Advocate for the Appellant.
Shri P. S. Reddy, Assistant Commissioner (AR) for the Respondent.
ORDER
Per: M.V. Ravindran
This appeal is directed against Order-in-Appeal No. HYD-EXCUS- MD-AP2-074-17-18 dated 25.09.2017.
2. Heard both sides and perused the records.
3. The issue involved in this case is regarding the rejection of refund claim filed by the appellant in respect of the claim of refund of the d

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Implication of GST & Income tax on purchase of a second hand machine

Implication of GST & Income tax on purchase of a second hand machine
Query (Issue) Started By: – Kishore Padav Dated:- 8-5-2018 Last Reply Date:- 9-5-2018 Goods and Services Tax – GST
Got 1 Reply
GST
Our Company had sold an equipment to a customer (A) in May 2017 @ ₹ 20 lakhs (incl. CST). The customer (A) has paid us only ₹ 7 lakhs till date.He has expressed his inability to pay the balance ₹ 13 Lakhs and has asked the company to take back his machine or help him sell his machine. Now we have found a customer (B) who has agreed to purchase the machine @Rs.13 Lakhs from him. Since the company has to recover ₹ 13 lakhs from csutomer (A), it is insisting on getting the payment to be made directly to them by

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Tax liability in case of change in constitution

Tax liability in case of change in constitution
Query (Issue) Started By: – JAY SHAH Dated:- 8-5-2018 Last Reply Date:- 9-5-2018 Goods and Services Tax – GST
Got 5 Replies
GST
Hello
We have a partnership firm and registered as composition dealer under GST regime. now i want to convert the same to proprietorship by retiring one partner and other one continue in same business under same banner. is there any tax liability arise on closing stock? in proprietorship also i want to continue under composition dealer.
Reply By kollengode venkitaraman:
The Reply:
WHEN THE BUSINESS OF THE PARTNERSHIP IS TAKEN OVER BY ONE PATNER AS A PROPRIETORSHIP, IT WILL BE EXEMPT "TAKING OVER A BUSINESS AS A WHOLE" IS EXEMPTED UNDER GST

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

o proprietorship. So tax liabilty of firm can be paid and ITC in proprietorship can be availed. But we are composition dealer. If we pay GST on closing stock in partnership firm for transfer of stock to proprietorship then we are going to pay two time GST. One at the time of transfer to proprietorship and again we have to pay gst in proprietorship on final sale.
Reply By KASTURI SETHI:
The Reply:
Dear Querist,
There is no doubt that afresh registration is required as rightly advised by Dr.Govindarajan, Sir.. When you apply for a new registration, you are to decide whether to opt for composition dealer or not. New registration, afresh option is required. It is natural that a composition dealer cannot avail ITC
Actually, no-provision o

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

CASE LAWS RELATING TO E-WAY BILL

CASE LAWS RELATING TO E-WAY BILL
By: – DR.MARIAPPAN GOVINDARAJAN
Goods and Services Tax – GST
Dated:- 8-5-2018

Implementation of e-way bill
The implementation of e-way bill has caused more delay because of the improvements to be done in the portal system. The Central Government has announced that the e-way bill system would be applicable for the inter-State transactions with effect from 01.02.2018 and the States would implement the e-way bill system for intra-State transactions by 1st June, 2018. Because of the glitches in the system, the Central Government postponed the implementation date and finally it has been implemented with effect from 01.04.2018. The States are advised to implement the same before 1st June, 2018.
E-way bill operations are now available for the following States-
* E-way bill operations are compulsory for intra-state movement of goods for Andhra Pradesh, Gujarat, Kerala, Telangana and Uttar Pradesh from 15th April 2018;
* E-way bill operatio

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

bill had not been downloaded. It has come on record that before seizure there was some problem in downloading the E-way Bill. The High Court directed to release the vehicles and goods subject to deposit of bank guarantee, equal to the value of the tax on goods.
In 'Abicor and Binzel Technoweld Pvt. Ltd. Versus The Union of India and Another' – 2018 (2) TMI 766 – BOMBAY HIGH COURT, the petitioner says that the Electronic Way Bills Rules have yet to come into force. Therefore, without access to the online profile, the petitioner cannot generate E-way bills. Without such E-way bills, the petitioner will not be allowed to move the goods anywhere and that will paralyze its business. Lack of access would mean that the petitioner is unable to file return or pay tax or undertake any other compliance required by the statute. The High Court held that the special sessions of Parliament or special or extraordinary meetings of Council would mean nothing to the assessees unless they obtain easy ac

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

tion of India. The High Court directed the first respondent to complete the adjudication provided for under section 129 after affording the petitioner an opportunity of hearing, within a week from the date of receipt of the order.
Seizure before effective date
In 'Modern Traders V. State of UP' – 2018 (4) TMI 1076 – ALLAHABAD HIGH COURT (decided on 03.04.2018) the goods were transported from Bhulandshahr to Delhi. There was no e-way bill during the movement of goods, while the vehicle was crossing Ghaziabad. The vehicle was intercepted and detained at Ghaziabad by the Assistant Commissioner, Mobile Squad on 24.03.2018. The vehicle was seized on the ground that there was no e-way bill. A show cause notice dated 28.03.2018 was issued under section 129(3) of the Act, The petitioner was directed to appear on 04.04.2018 and explain as to why the tax @ 18% and equivalent amount of penalty may not be imposed. The petitioner, therefore, approached the High Court invoking writ jurisdiction.

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ing the e-way bill with respect to inter-State transaction is mandatory with effect from 01.04.2018, whereas in the present case the transaction is much before the aforesaid date. The High Court directed respondent No. 3 to release the goods and vehicle.
In 'M/s Bhumika Enterprises V. State of U.P. And 3 Others' – 2018 (4) TMI 530 – ALLAHABAD HIGH COURT, from perusal of the record the High Court have noticed that the vehicle has been detained and the goods/vehicle was seized by the respondent no.4 on 27.3.2018 whereas the time has been granted for submission of reply and appearance of the person concerned before the respondent no.4 on the later date. There is no dispute with regard to quality and quantity of the goods and further that the invoice issued clearly indicates of charge of C.G.S.T. and S.G.S.T by the petitioner. The High Court further noticed that there is no dispute with regard to registration of the seller (the petitioner) and the purchaser as also that the goods were bei

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

IN number of some dealer situates at Allahabad but no details of the said dealer has been given in the impugned seizure order nor the details of the mobile number holder.
Since the tax invoice indicating the tax charged and the same admittedly found during the course of inspection/detention and E-way bill-02 has been downloaded much before the seizure order, the High Court saw no justification in the impugned seizure order and therefore, the High Court have no option but to allow the present writ petition and to set aside the seizure order dated 27.3.2018 as well as the show cause notice issued under Section 129(3) of the Act for imposition of penalty.
Justification for seizure
In 'Surendra Steel Supply Company Versus State of U.P. And Another' – 2018 (5) TMI 526 – ALLAHABAD HIGH COURT, (decided on 11.04.2018) the vehicle carrying the goods was intercepted at Kanpur on 01.04.2018 at about 9-30 a.m. by respondent no. 2 and interception/detention memo was issued on the ground that sin

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

and seizure.
* Even though E-Way Bill No.01 was generated and produced by the petitioner but there was no requirement for the same as the Central Government has suspended the requirement of E-Way Bill No.01 on 01.02.2018.
The Revenue has not been able to justify the impugned order in the facts and circumstances of the case. The High Court required respondent no.2-Assistant Commissioner, Commercial Tax, Mobile SquadXI, Kanpur, U.P. to appear before the Court day after tomorrow (13.04.2018) to explain as to under which authority of law he intercepted the vehicle and passed the seizure order despite E-Way Bill No.01 was generated and produced.
Non mentioning of vehicle number
In 'VSL Alloys (India) Pvt. Ltd. Versus State Of U.P. And Another' – 2018 (5) TMI 455 – ALLAHABAD HIGH COURT, (decided on 13.04.2018) the detention was made on the ground that Part-B of e-way bill was incomplete. The contention of the petitioner before the authority below was that there was no intention on the

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Transportation of Employees

Transportation of Employees
Query (Issue) Started By: – Kusalava InternationalLimited Dated:- 8-5-2018 Last Reply Date:- 22-6-2018 Goods and Services Tax – GST
Got 34 Replies
GST
we are mfg co and provide transportation facility to employee from home to factory and factory to home for that we have purchased bus and given to one person(Unregistered Person) to run bus.For that we are paying every month bill to him.(including Diesel,Driver Salaries and his commission)
1.What is the rate of GST to be charged on Bill if he is registered?Please refer SAC Code.
2.Can we claim ITC on that bill?
Reply By Praveen Nair:
The Reply:
* SAC – 9964 @18%.
* As per section 17(5) of the CGST Act input tax credit shall not be available in respect of motor vehicles and other conveyances except when they are used for making the following taxable supplies;
* Further supply of such vehicles or conveyances.
* Transportation of passengers.
* Imparting training on driving, flying, navi

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

p and dropping the employees from a fixed pick up point to factory and then dropping at the same fixed point. This service cannot be classified in the nature of personal consumption either as the activity is related to business only. Further this transportation service cannot be classified under rent-a-cab service. As such, I feel, GST input tax credit is available in this case. would invite experts counter opinion on this.
Reply By Alkesh Jani:
The Reply:
Sir,
For ready reference please allow me to reproduce relevant portion of Section 17(5) of CGST, Act, 2017.
“(5) Notwithstanding anything contained in sub-section (1) of section 16 and sub-section (1) of section 18, input tax credit shall not be available in respect of the following, namely:-
(a) motor vehicles and other conveyances except when they are used
(I)for making the following taxable supplies, namely:-
(A) further supply of such vehicles or conveyances ; or
(B) transportation of passengers; or…..”
For better

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

. Moreover, in GST motor vehicles has been mentioned, therefore, it can be said that all motor vehicles as defined under Motor Vehicles Act, 1988, are covered under “Rent-a-cab” service.
Based on above, I am of the view that ITC is not available in the instant case.
Our experts may correct me if mistaken.
Thanks
Reply By KASTURI SETHI:
The Reply:
Sh.Alkesh Jani Ji, Top most reply. Crystal clear interpretation.
Reply By JSW CEMENTLIMITED:
The Reply:
Sh Alkesh Janiji, appreciate your analysis. But, still I am of the same view that credit of service provided by using the company's bus is available to a manufacturer on the following ground.
In the absence of definition of cab in GST Act, you have to refer the definition given other existing law in force viz; motor vehicle Act only and not repealed law (i.e.section 65(20) of Finance Act which was in in force till 30.06.2012). During Service tax regime, credit on transportation of employees were not available and department has

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

mportant, the meaning given in the Cambridge dictionary is “cab means the separate front part of a large vehicle, such as a truck, bus, or train, in which the driver sits”. Now rent-a-cab means renting of the space which controls the motor vehicle. The bus falls as motor vehicle having capacity of carrying more than 12 passengers and falls with the ambit of “Rent-a-cab” service.
Repeating that an employee cannot be termed as “passenger”. If I accept your contention that bus is not a cab then too it is covered under Section 17(5)(a)(i)(B) of CGST Act, 2017, ITC with regards to motor vehicle except for transportation of passenger, is not available.
Let me thank Sh. Kasturiji,Sir for expressing their views.
Our experts may correct me if mistaken.
Thanks
Reply By JSW CEMENTLIMITED:
The Reply:
Sir,
Here the queriest is not asking for eligibility of ITC on Bus, but his query is with regard to services availed for transportation of employees. ITC on buses purchased for the purpose of t

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Reply By Alkesh Jani:
The Reply:
Sir, In this case also, I am of the view that ITC on the expenses incurred to run a bus, is not available. As this is the facility extended to the employee by the employer, this service is not obligatory for an employer to provide to its employee under any law for the time being in force. However, as there are various decision in the erstwhile law allowing the Credit as input service but that depends upon the facts and circumstances of the case. Further, it is onus on the assessee to prove the nexus.
Request for comments.
Thanks
Reply By JSW CEMENTLIMITED:
The Reply:
Sir
Presently, most of the companies are located in remote areas away from the city, and almost all the companies are providing pick and drop facilities to its staff and sub-staffs for the reason that they reach office and plant in time so that production is not hampered. This facility may be seen as a facility given to employee for the benefit of business only. Unless there is busine

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ent's intention is not to allow ITC . It is also the intention of legislature. The definition of cab would not help. In my view , the case is not worth fighting. However, there is a slim chance on the ground of challenging the definition of 'passenger' in this context.
Reply By JSW CEMENTLIMITED:
The Reply:
Kasturi sir
I respect your interpretation and experience also. Still I am not convinced as to why we are comparing employees with passenger, employer employee relationship and all. The service is not falling under rent a cab service where eligibility is restricted except it is performed under as an obligation under some law, it can not be said to be a welfare facility, it is used for furtherance of business, it helps people to reach workplace in time attend to their duty timely,. Directly or indirectly it has a bearing on the manufacturing business, still all the experts are negative towards eligibility.
Reply By Alkesh Jani:
The Reply:
Sir, I agree that by way of d

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

essee), in most of the cases the amount is very small compared to the annual turnover, and small entrepreneurs cannot afford the litigation and cost for the same. The grounds of notice, orders and appeal and person representing the case is important and than too the decisions may not be expected or favorable. The case law, as on now, have not attained its finality, I may agree with the contention in future.
Please offer your comments and correct me if mistaken.
Thanks,
Reply By Anubhav Bansal:
The Reply:
Deal All,
I went through entire discussion in this thread which mainly is on eligibility of ITC in this case of services.
Now, I seek experts opinion on what will be the GST treatment of this service in hands of the Company when they are giving this service to employees i.e. will it be consider as "supply" in terms of the provision of CGST act and will company have to discharge GST liability in case:-
1. When the company is recovering partial amount towards this servic

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

TLIMITED:
The Reply:
What is specified in Section 25 as referred to in entry no.2 of schedule I
Reply By Anubhav Bansal:
The Reply:
Dear JSW ji,
Extract of Section 25 for ready purusal:
"ACTIVITIES TO BE TREATED AS SUPPLY EVEN IF MADE WITHOUT CONSIDERATION 1. Permanent transfer or disposal of business assets where input tax credit has been availed on such assets. 2. Supply of goods or services or both between related persons or between distinct persons as specified in section 25, when made in the course or furtherance of business: Provided that gifts not exceeding fifty thousand rupees in value in a financial year by an employer to an employee shall not be treated as supply of goods or services or both."
Further, as per the explanation to section 15, for the purposes of CGST Act:-
(a) persons shall be deemed to be "related persons" if –
(i) ………..;
(ii) ……..;
(iii) such persons are employer and employee;
Conjoint reading of this 2 provisions of t

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

n common parlance, gift is made without consideration, is voluntary in nature and is made occasionally. It cannot be demanded as a matter of right by the employee and the employee cannot move a court of law for obtaining a gift. Another issue is the taxation of perquisites. It is pertinent to point out here that the services by an employee to the employer in the course of or in relation to his employment is outside the scope of GST (neither supply of goods or supply of services). It follows therefrom that supply by the employer to the employee in terms of contractual agreement entered into between the employer and the employee, will not be subjected to GST. Further, the input tax credit (ITC) scheme under GST does not allow ITC of membership of a club, health and fitness centre [section 17 (5) (b) (ii)]. It follows, therefore, that if such services are provided free of charge to all the employees by the employer then the same will not be subjected to GST, provided appropriate GST was p

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

general entry.
Further, it is advisable to the person, rather than hiring a person for providing such transportation services, the manufacturing company should employ someone to run such buses at its own cost. This will somehow save the commission cost being paid by the manufacturing company to the person.
Reply By HIREGANGE& ASSOCIATES:
The Reply:
My views are as below:
a): 17 (5) (a) not applicable as it blocks credit on "supply of motor vehicles" when supplied "as such" but not on the services provided by using such motor vehicle. Accordingly, no need of considering definition of passenger/employee etc.
b) Restriction in 17 (5) (iii) is on the rent a cab not renting of motor vehicle. Erstwhile Cenvat Credit Rules excluded from the definition of input services "services provided by way of renting of a motor vehicle". If the intention of law makers under GST was to disallow credit on buses, they could have used similar language. (i.e. motor vehicle

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

that ITC is not admissibie .
Reply By Mahadev R:
The Reply:
I wish to agree with Mr.Venkat Raman, Credit restriction should be in relation to motor cab or maxi cab which would cover upto 12 persons. In other cases, credit should be allowed and it would be allowed as gradually credits would become more seamless in future.
Reply By YAGAY and SUN:
The Reply:
Get it clarified from the Law Makers as there are certain words on which no definition is provided in the GST Law.
Reply By Anubhav Bansal:
The Reply:
Dear Venkat Ramanji,
Thanks for sharing the extract of those advertisement. After reading it, I am of the opinion that your conclusion basically is relied upon following extracts of the advertisment "it follows therefrom that supply by the employer to the employee in terms of contractual agreement entered into between the employer and the employee, will not be subjected to GST. "
If this be the case then even the partial recovery form the employee can be said to be a

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

s except when they are used
(i) for making the following taxable supplies, namely:-
(A) further supply of such vehicles or conveyances ; or
(B) transportation of passengers; or
(C) imparting training on driving, flying, navigating such vehicles or conveyances;
(ii) for transportation of goods;
Based on above, it is clear that law has very specifically conveyed that ITC is available ONLY for taxable supply i.e. (i) further supply of such vehicles, (ii) for transportation of passengers or goods and (iii) imparting training. In my point of view drop and pick up of employee does not fall within this “namely” services. Moreover, supplies to employer to employee has specifically mentioned in Section and schedules, wherever, benefit is to be granted. So only those supplies including gifts, where specifically mentioned is available to employer. So, I am of the view that ITC is not available.
Thanks
Reply By Anil Sood:
The Reply:
Friends let us have a look at the Apportionment & bl

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

rd supply of goods or services or both of a particular category is used by a registered person for making an outward taxable supply of the same category of goods or services or both or as an element of a taxable composite or mixed supply;
(ii) membership of a club, health and fitness centre;
(iii) rent-a-cab, life insurance and health insurance except where
(A) the Government notifies the services which are obligatory for an employer to provide to its employees under any law for the time being in force; or
(B) such inward supply of goods or services or both of a particular category is used by a registered person for making an outward taxable supply of the same category of goods or services or both or as part of a taxable composite or mixed supply; and
(ii) travel benefits extended to employees on vacation such as leave or home travel concession;
Now, if we look at the definition, the credit of motor vehicle is inadmissible except in the case of buses owned by the Employer becau

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

GST on Train Food & Water: Charge Based on Goods' Value Only, Exclude Service Charges, No Service Element Involved.

GST on Train Food & Water: Charge Based on Goods' Value Only, Exclude Service Charges, No Service Element Involved.
Case-Laws
GST
Rate of GST – supply of food on board the trains – it is not possible to classify the whole contract as supply of services – The supply of goods i.e. food, bottled water etc. shall be charged to GST on value of goods (excluding the service charges) at applicable rates as pure supply of goods, as the same have no element of service. – AAR
TMI Updates – Hig

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Newspapers Supplied on Trains Exempt from GST Under Notification No. 2/2017, S. No. 120.

Newspapers Supplied on Trains Exempt from GST Under Notification No. 2/2017, S. No. 120.
Case-Laws
GST
Supply of newspaper on board the trains – The supply of newspaper is separately invoiced

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

AAR advises using interpretative rules to determine correct HSN code for billing mixed materials with one primary component.

AAR advises using interpretative rules to determine correct HSN code for billing mixed materials with one primary component.
Case-Laws
GST
Before AAR, the following question was raised: I would like to know if there is a combination of different materials and about 75% (value terms) is getting used of any one Raw Material, under which HSN should we make bill? – AAR advised the applicant to understand the interpretative Rules and determine the classification accordingly.
TMI Updates

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Trophies Not Universally Classified Under HSN Code 83062920; Must Follow Customs Tariff Headings Provisions.

Trophies Not Universally Classified Under HSN Code 83062920; Must Follow Customs Tariff Headings Provisions.
Case-Laws
GST
Classification – TROPHY – even though the word TROPHY is specificall

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

RATE DIFFERENCE CREDIT NOTE ISSUED BY OUR SUPPLIER AGAINST PURCHASE

RATE DIFFERENCE CREDIT NOTE ISSUED BY OUR SUPPLIER AGAINST PURCHASE
Query (Issue) Started By: – nandankumar roy Dated:- 8-5-2018 Last Reply Date:- 8-5-2018 Goods and Services Tax – GST
Got 2 Replies
GST
DEAR SIR,
SUPPLIER OR CREDITORS ISSUED CREDIT NOTE AGAINST RATE DIFFERENCE THAT IS SHOWING IN GSTR2 CAN WE WE TAKE THIS AMOUNT IN OUR GSTR1 BY TREAT AS DEBIT NOTE OR WHETHER CREDITORS REFLECTED ITC AMOUNT ONLY TO BE REVERSE IN 3B RETURN TILL HAVE TO WAIT SUBMISSION OF GSTR2 IN FUTUR

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

“Sulekh Sarita” Classified as Workbook Under Heading 48.20, Lacks Features for Heading 49.03 Classification.

“Sulekh Sarita” Classified as Workbook Under Heading 48.20, Lacks Features for Heading 49.03 Classification.
Case-Laws
GST
Classification of books – Work Books or Exercise Book – Sulekh Sarita – presence of printed text does not affect their classification under heading 48.20 as exercise books – Further, since, none of the books contain any pages with children’s picture, drawing or colouring matter, classification of any of them under heading 49.03 is not possible – AAR
TMI Update

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

M/s R.N. Metal (India) Pvt. Limited, R.N. Sharma, Managing Director Versus CCE & GST, Jaipur

M/s R.N. Metal (India) Pvt. Limited, R.N. Sharma, Managing Director Versus CCE & GST, Jaipur
Customs
2018 (5) TMI 687 – CESTAT NEW DELHI – 2019 (366) E.L.T. 568 (Tri. – Del.)
CESTAT NEW DELHI – AT
Dated:- 8-5-2018
Custom Appeal Nos. 50529 & 50482 of 2018 – Final Order Nos. 51709 – 51710/2018
Customs
Hon'ble Mr. Justice ( Dr. ) Satish Chandra, President Hon'ble Mr. V. Padmanabhan, Member ( Technical )
Ms. Nupur Maheshwari, Advocate for the appellant
Sh. Rakesh Kumar, AR for the respondent
ORDER
Per : V. Padmanabhan
The present appeals are against the Order-in-Appeal No. 256 to 257(SM)CUS/JPR/2017 dated 15.11.2017.
2. The appellant imported certain goods and filed two Bills of Entry declaring the import of 'Alloy Steel Melting Scrap' falling under Tariff item 72042990 of the Customs Tariff. The Customs authorities opened and examined all the ten containers covered under the two Bills of Entries and found that seven containers were stuffed with the declared it

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ds were used or not cannot be ascertained by chemical test. Sample of the goods sent to National Test House, Government of India begot the opinion that the grinding balls imported were not as per IS Standard in terms of hardness and chemical composition.
5. Opinion of Shri I.P.S. Arora, Chemical Engineer was also obtained at the instance of the appellant who stated that the grinding media balls were found with deep cuts and varying dimensions.
6. In the above scenario, show cause notice dated 08.05.2014 was issued by the Customs Department which resulted in the Order-in-Original dated 10.11.2014 in which the charge of mis-declaration was upheld; the 'Grinding Media Balls' were ordered for reclassification and differential duty was charged. Imported offending goods were ordered for confiscation and allowed for redemption. Penalties were also imposed on the appellant as well as Sh. R. N. Sharma, Managing Director.
7. When the issue was challenged by the appellant before the Commission

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

are alloy steel melting scrap. Since the inspecting agency is approved by the DGFT, such certificate is to be accepted.
(ii) The report issued by the CRCL has stated that the fact whether the imported goods were new or old cannot be ascertained by chemical analysis but the test report from National Test House, which is a Government agency, has opined that the samples tested were of grinding balls but which did not satisfy the IS standards.
(iii) The certificate issued by the Chartered Engineer Sh. I.P.S. Arora has categorically stated that the grinding balls were found with deep cuts indicating that such goods were old and hence scrap.
In view of the above evidences in support of the appellant, the charge of mis-declaration cannot be sustained.
(iv) The appellant has also requested for allowing clearance of the goods after mutilation. This will ensure that the goods cannot be utilised for any purpose other than as scrap for melting but such request has been denied by the Depar

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

. But amidst the declared melting scrap, the examination by Customs Officers revealed that 'Grinding Media Balls' were found which were new and unused. Such balls can also be considered as scrap only if they were new and old.
14. The proceedings before the lower authorities have taken twists and turns with contrary opinions expressed by different experts. The opinion given by CRCL as well as National Test House has been of little help in deciding the controversy one way or other. The three experts whose opinion was taken by the Customs Department took the view that the impugned goods were 'Grinding Media Balls' which were new and unused. During the cross examination of these experts before the Commissioner (Appeals), they have stood by their opinion but the other expert Sh. I.P.S. Arora, Chartered Engineer who has originally given the opinion that there were deep cuts and were of varying dimensions retracted his original view during cross-examination.
15. It has been emphasised again

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

heading there is no precondition of fulfilment of condition of specification as per IS standard. As well as in all the report of experts, every expert including National Test House, CRCL, independent expert, chartered engineer have accepted that goods in questions are Grinding Media Balls. As regards whether the imported grinding media balls are new or old one, in my opinion the same can be verified by visual inspection of all the three experts sh. B. K. Sharma, Sh. P.C. Sanghi and Sh. V. K. Sanghi have opined that the goods imported were Grinding Media Balls. As regards National Test House reports it is provided that goods examined by them are grinding media balls having size as per packing slip and ball diameter within specified value, but not confirming to the IS specification in respect of hardness and chemical composition. Sh. Rakesh Saini, Scientist Incharge of National Test House in his statement has stated that as their test house is not technically equipped to test and make co

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

M/s Multiplex Cinevision Pvt. Ltd. Versus State Of UP And 2 Others

M/s Multiplex Cinevision Pvt. Ltd. Versus State Of UP And 2 Others
GST
2018 (5) TMI 762 – ALLAHABAD HIGH COURT – 2018 (14) G. S. T. L. 3 (All.) , [2018] 59 G S.T.R. 206 (All)
ALLAHABAD HIGH COURT – HC
Dated:- 8-5-2018
Writ Tax No. 751 of 2018
GST
Hon'ble Krishna Murari And Hon'ble Ashok Kumar, JJ.
For the Petitioner : Asha Parihar
For the Respondent : C.S.C.,Gyan Prakash
ORDER
Petitioner is a Company incorporated under the provisions of the Companies Act engaged in the business of construction and development of entertainment facilities including Multiplex theatres in district Meerut. Under the U.P. Entertainments and Betting Tax Act, 1979 (hereinafter referred to as the Act) an scheme was formulated on 3rd

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

bility acquired, accrued or incurred under the repealed Act provided the tax exemption granted under the repealed Act by any notification has not been rescinded or revoked by a fresh notification on or after the enforcement of the G.S.T.
The submission of learned counsel for the petitioner is that in view of Section 174 of the U.P.G.S.T. as there is no notification repealing the benefit conferred upon the petitioner under the scheme of the Act, he is entitle to collect entertainment tax as in the past upto 24.11.2018 and to retain the percentage of it in accordance with the scheme.
Learned Standing Counsel appearing for the respondents No. 1 and 3 and Sri Vaibhav Tripathi, who has accepted notice on behalf of respondent No.2 are directed

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

IN RE : MAHARASHTRA STATE POWER GENERATION COMPANY LIMITED

IN RE : MAHARASHTRA STATE POWER GENERATION COMPANY LIMITED
GST
2018 (5) TMI 1332 – AUTHORITY FOR ADVANCE RULING – MAHARASHTRA – 2018 (13) G. S. T. L. 177 (A. A. R. – GST), [2020] 75 G S.T.R. 180 (AAR)
AUTHORITY FOR ADVANCE RULING – MAHARASHTRA – AAR
Dated:- 8-5-2018
GST-ARA-15/2017-18/B-30
GST
Shri B. V. Borhade, Joint Commissioner of State Tax and Shri Pankaj Kumar, Joint Commissioner of Central Tax
PROCEEDINGS
(under section 98 of the Central Goods and Services Tax Act, 2017 and the Maharashtra Goods and Services Tax Act, 2017)
The present application has been filed under section 97 of the Central Goods and Services Tax Act, 2017 and the Maharashtra Goods and Services Tax Act, 2017 [hereinafter referred to as “the CGST Act and MGST Act”] by MAHARASHTRA STATE POWER GENERATION COMPANY LIMITED, the applicant, seeking an advance ruling in respect of the following :-
    1) Whether GST is applicable on Liquidated Damages in case of,-
  &

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

has occurred after GST roll but, whether GST will be applicable to the Liquidated Damages imposed for entire period of delay or to the period falling after GST roll-out? In case when GST is to be imposed for period after date of GST rollout but due to maximum capping of LD, the amount of LD is calculated at given percentage instead of being period-based, then how GST needs to be levied.
        d) Whether the contractor/vendor will be able to utilize the amount of LD imposed over him as Input Tax Credit subject to satisfying all other conditions?
    At the outset, we would like to make it clear that the provisions of both the CGST Act and the MGST Act are the same except for certain provisions. Therefore, unless a mention is specifically made to such dissimilar provisions, a reference to the CGST Act would also mean a reference to the same provision under the MGST Act. Further to the earlier, henceforth for the purposes of this Adva

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ties. In this case, if there is delay on the part of the contractor to provide materials / services; Liquidated damages (LD) are deducted from the amount payable to vendor. The L.D so deducted is treated as income
    Type 2 : Construction of new power plants or renovation of old plants
    In this regard, normally the contract is awarded to vendors to build the plant on Turnkey basis. Normally the contracts are awarded in three parts, supply of materials, erection & commissioning and Civil work. As per terms and conditions, the period of completing the contract is fixed. When plant construction is completed, the actual time taken for completion of contract is calculated. If there is delay in completing the contract, the assessment regarding party responsible for delay is made. If the delay is on account of contractor, then Liquidated damages (LD) are calculated as per contract terms and levied upon the contractor.
    In accounting, the

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

terming the LD as a consideration towards a service provided by the company to the contractor requires clarification.
    For the sake of better understanding, clauses relating liquidated damages from one of the contracts pertaining to erection, testing and commissioning is reproduced below –
    “7.0 LIQUIDATED DAMAGES FOR DELAY IN ERECTION, TESTING AND COMMISSIONING
    7. 1 The Contractor shall strictly adhere to the Protect completion schedule to achieve the trial operation in accordance with the project completion schedule. In case the Contractor fails to achieve successful completion of Trial Operation due to delay on his part, then the Owner shall levy liquidated damages.
    7.2 Time Schedules indicated for various activities are for the purpose of monitoring to ensure work completion as per Project Completion Schedule. Only the successful completion of Trial Operation of the unit shall be considered for the purpo

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

the Contractor, as may be deemed fit in the interest of completing the balance works
    7.6 If the contractor fails to achieve the Trial Operation of the unit within the time period specified in the Project Completion Schedule due to reasons attributable to him then the owner shall levy Liquidated damages on the Contractor @12% of the contract price for erection, testing and commissioning (excluding insurance charges, taxes and duties) along with applicable price variation per week of delay or part thereof subject to the maximum 10% of the contract price for erection, testing and commissioning (excluding insurance charges, taxes and duties) along with applicable price variation.”
Similar clauses are there in supply, civil and structural work of the contract.
Submission dt. 08.02.2018
    I. STATEMENT OF FACTS
    1. The Maharashtra State Power Generation Company Ltd (hereinafter referred to as applicants) is engaged in generation of po

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ct completion schedule to achieve the trial operation units 8 & 9 by 41 and 44 months respectively. In case the Contractor fails to achieve successful completion of Trial Operation within specified time period as per the project completion Schedule due to delay on his part, then the Owner shall levy liquidated damages.
    7.2 Time Schedules indicated for various activities are for the purpose of monitoring to ensure work completion as per Project Completion Schedule. Only the successful completion of Trial Operation of the unit shall be considered for the purpose of levy of Liquidated Damages.
    7.3 The payment by Contractor or deduction by Owner of any sums under the provision of this clause shall not relieve the Contractor from his obligations to complete the works or from his other obligations under the contract.
    7.4 The liability of payment of these liquidated damages by the Contractor will be established once the delay in succ

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

uding insurance charges, taxes and duties) along with applicable price variation per week of delay or part thereof subject to the maximum 10% of the contract price for erection, testing and commissioning (excluding insurance charges, taxes and duties) along with applicable price variation.”
    7.7 For the purpose of deciding the amount of Liquidated Damages on the erection price, contract price along with the applicable price variation (excluding taxes, duties and insurances charges.) as per contact price adjustment shall be considered.
    Further Liquidated Damages for each unit shall be levied separately and for this purpose, price of one unit shall be half of the price of both the units.
    Similar clauses are there in supply of balance of plant package, erection testing and commissioning of balance of plant package, supply of main plant package, civil and structural works of balance of plant package and various another contract ent

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

lassified under the category in which the services of the contractor are classified?
        c) Whether the GST on liquidated damages is covered under Schedule II entry no.5(e) vide HSN code 9997-Other Services rate 18% is correct or any other entry is relevant?
        d) what will be construed as the time of supply. Will it be the period in which delay is occurring or it is the time when decision to impose liquidated damages is taken?
        e) If some part of delay has occurred before GST roll-out and some part of delay has occurred after GST roll-out, whether GST will be applicable to the liquidated damages imposed for entire period of delay or to the period falling after GST roll-out? In case when GST is to be imposed for period after date of GST rollout but due to maximum capping of liquidated damages, the amount of liquidated damages is calculated at given percentage inst

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

d by the applicant. The applicant relies upon the following judgments:-
            a) Commissioner of Chandigarh v/s. M/s. HFCL 2015(11)-TMI-893-CESTAT
            b) M/s. Victory Electricals Ltd. 2013-(298)-ELT-534
        Reliance is placed on Australian Ruling issued under the Australian Goods & Service Tax Act, 1999:
        The Australian Goods & Service Tax Act, 1999 defines 'supply' u/s. 9-10(1) as follows:
        A supply is any form of supply whatsoever.
        The Sub-Section 9-10(2) further provides as follows:
        Without limiting sub-section (1), supply includes any of these:-
            (a) a supply of goods;
&nbs

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

i) to tolerate an act or situation;
            (h) any combination of any 2 or more of the matters referred to in paragraphs (a) to (g).
        Rulings are issued by Australian Tax Authority to interpret and clarify the provisions of GST law prevailing in that country. The ruling is an expression of the Commissioners opinion about the way in which the relevant provision applies or would apply to the entities, generally to a class of entities in relevant to a particular scheme. The Commissioner issued the public ruling on the payment of damages on early termination of lease of goods, cancellation of contracts and out of court settlements where in they had discussed the taxability of the liquidated damages. The same along with cases and books has been discussed as follows:-
* In GSTR 2003/11 of Goods and service tax ruling relating to payment on early termination of lease of goods, it was clar

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

damage, negligence causing loss of profits, breach of copyright, wrongful use of trade name, personal injury, termination or breach of contract In such cases, there is therefore no GST liability. ”
        Thus, Australian GST has treated the payment of liquidation damages as part of the same supply and mere re-determination of the consideration of the same supply if the has been specified in the original contract i.e. if liquidation of damages are to be borne by the service provider then same will be considered as towards deficiency of services and thereby reduces the original consideration and it will not be considered as separate service and hence it is not covered by the term Obligation to tolerate an act or a situation'
        The deficiency of service may arise on account of poor quality of service or delay in rendering the service and therefore it is our interpretation that deduction of the contract pr

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

tractor. The CBEC vide Circular No. 144/13/2011 dated 18/07/2011 has clarified that the services are completed only when the auxiliary activities for the purpose of raising invoice has also been completed. The para 2 of the Circular is reproduced below:
        “2. These representations have been examined. The Service Tax Rules, 1994 require that invoice should be issued within a period of 14 days from the completion of the taxable service. The invoice needs to indicate inter alia the value of service so completed. Thus, it is important to identify the service so completed. This would include not only the physical part of providing the service but also the completion of all other auxiliary activities that enable the service provider to be in a position to issue the invoice. Such auxiliary activities could include activities like measurement, quality testing, etc. which may be essential pre-requisites for identification of completion of service. The t

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

or deduction of Liquidated Damages.
        f) The contractor and vendor will be entitled to the credit if any, payable on the Liquidated Damages as the expense is incurred in the course or furtherance of business. Therefore, it is an input service used by him in the course of supplying the services. The interpretation given for para (b) to (f) is without prejudice to our interpretation that no GST is payable, as the deduction of Liquidated Damages does not amount to supply of any services.
        Additional submission by the applicant on 27.02.2018
        In addition to the re-submissions made on certain portion of our application for advance ruling, the applicant would like to submit the following additional submissions in support of its view: –
        1) Determination of Transaction value.
        a. Cl

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

e duty was payable after considering the amount of Liquidated Damages:
        1. COMMR. OF C EX.. CHANDIGARH-l Versus H.F.C. L . (WIRELESS DIVISION) 2015 (11) TMI 893 – CESTAT NEW DELHI
        2. VICTORY ELECTRICALS LTD 2013 (290) E.L.T. 534 (Tri. – LB) = 2013 (12) TMI 81 – CESTAT CHENNAI
        3. MRS. Priyaraj Electronics Ltd Versus Commissioner of Central Excise Bangalore   2016 (6) TMI 873 – CESTAT BANGALORE
        4. UNITED TELECOM LTD 2006 (204) E.L.T. 626 (Tri. – Bang.) = 2006 (9) TMI 321 – CESTAT, BANGALORE
        b. Under GST law section 15(1) of the CGST act,
        15. (1) The value of a supply of goods or services or both shall be the transaction value, which is the price actually paid or payable for the said supply of goods or services or both wher

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

      The contract may prescribe damages for deficiency in the performance of contract known as 'liquidated damages'. It is to dissuade unsatisfactory performance or non-performance. For instance, contracts state that lime is the essence of contract, and any delay invites say, 1/2% or 1% of the value of the contract for every week of delay and the like. Similarly, it is common to forfeit earnest money deposit (EMD) from a bidder in case he wins the bid but fails to act thereafter. This forfeiture clause is a deterrent for non-serious bidders entering the fray. Other examples may be rent for delay in lifting goods; agreeing to shoulder testing charges for samples to meet standards; cost of removing rejected goods, etc
        Payment of damages, deducting the liquidated damages or the forfeiture of deposit does not restitute the person to whom loss or damage is caused. Liquidated damages are in nature of a measure of d

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

y plates and other chemicals and take X-ray photographs of patients according to requisitions from physicians as also of his own patients.
        After taking the X-ray, he used to give technical advice to his patients and was charging a flat rate towards his remuneration and cost of materials. Sales Tax Officer was of the view that the turnover arising from such transactions was liable to tax under the Act. The hon'ble High Court of Orissa held that;
        'Mere passing of property in an article or commodity during the course of the performance of the transaction in question does not render it a transaction of sale. For, even in a contract purely of work or service, it is possible that articles may have to be used by the person executing the work and property in such articles or materials may pass to the other party. That would not necessarily convert the contract info one of sale of those materials. In

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

separate and distinct supply' from that of the LSTK's scope and ambit seems to be a bit too far stretched.
        If this argument is found to have some merit, then what could possibly attract levy of GST under the impugned clause could be an arrangement where primary intention is to tolerate an act or a situation.
        4) Revised amount in case of renegotiation will be the amount of consideration
        Further, the CBEC, vide their circular dated 31.03.2011, clarified the service tax rule, 1994, explaining that in case of renegotiation of the amount of consideration in terms of the contract, then the service tax will be payable on such revised amount, subject to the fact that the excess amount is either refunded or a suitable credit note is issued to the service receiver the relevant extract reads as follows:
        11. Changes

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

the term and conditions laid down in the contract, then service tax/GST will be payable on the renegotiated amount.
        Additional submission on 07.03.2018
        1. We thank you very much for patient hearing on 28.02.2018 on the above application. As submitted during the hearing following additional submission/documents are submitted: –
        i) Manner of Recovery.
        As directed, a specimen running bill raised by M/s Bharat Heavy Electricals Limited, bearing no. MS/PW/9515/13/1027(89) is attached as Annexure -l. ln this case 15% of the invoice amounting to Rs. 56,29,471/- has been deducted as retention This amount is deducted on invoice value of Rs. 3,75,29,810/-
        For the sake of clarification as to retention @ 15% towards LD, when the maximum limit of LD is prescribed at 10%, it is to su

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

tion is transferred to LD Account and LD amount is then transferred to project cost and as such Project cost is reduced to that extent.
        This explains the manner in which the recovery of liquidated damages is made by the applicant.
        ii) amount not retained for toleration of Act.
        During the hearing the query regarding taxability under the toleration of an act was discussed. It was submitted that the liquidated damage is part of the contract for supply of equipment and service. It is not a separate contract of toleration of an act for which payment is made.
        The applicant had attached one of the contracts with M/s BHEL as specimen. It was submitted that it was one single contract for supply of goods and services and not two contracts for supply of goods services and toleration of an act. The Divisible contract has bee

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ion and apportionment, having two or more parts, in respect to matters and things contemplated and embraced by it, not necessarily dependent upon each other, or intended by parties as being dependent Gross v Maytex Knitting Mills of Cal.. 116 C.A. 2d 705, 254 P. 2d 163, 167 See separability clause.
        When a contract is severable, a breach may be found to constitute a default as to only the specific part breached, thus relieving the defaulting party from liability for damages for breach of the entire contract
        Hence, the execution of the contract and deduction cannot be enforced separately. The delay in supply will always precede deduction of liquidated damages, thus, deduction of liquidated damages cannot be independently enforced. Hence it is submitted that the contract is for single supply and not for the two supplies. In any contract if the activities are depended on each other and it cannot be perf

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

nalty will be added to the consideration of the supply. They will not be considered as a separate supply of toleration of an act. The penalty will be leviable for breach of any condition of contract. The penalty as per statutory provision is therefore has been considered as a part of value of supply and not as amount received for toleration of an act. Similarly, interest will be charged for delay in making payment by the recipient. The interest therefore cannot be considered as part of amount received for toleration of an act or delay in making payment.
        In view of the above, it is submitted that the liquidated damages cannot be considered as amount received for tolerating an act.
        2. Liquidated damages are recovered for compensating the loss suffered by the recipient. The section 73 and section 74 of the Indian Contract Act, 1872 provides for recovery of liquidated damages in case of breach of contra

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.
Explanation. A stipulation for increased interest from the date of default may be a stipulation by way of penalty.
Exception. When any person enters into any bail-bond, recognizance or other instrument of the same nature, or, under the provisions of any law, or under the orders of the 2[Central Government] or of any [State Government], gives any bond for the performance of any public duty or act in which the public are interested, he shall be liable, upon breach of the condition of any such instrument, to pay the whole sum mentioned therein.
Explanation. A person who enters into a contract with Government does not necessarily thereby undertake any public duty or promise to do an act in which the public are interested.
        It has been consistently held that liquidated damage is to compensate the person for loss

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ract will not be in the form of compensation of a loss suffered by recipient of service. In this case, the amount deducted is only for compensate and not for toleration of an act. Therefore, not a separate supply liable for tax. Hence, no GST is payable. The above submission shall be considered while deciding the application.
        03. CONTENTION – AS PER THE CONCERNED OFFICER
        The submission of the jurisdictional authority is as follows-
        “Comments against questions/issues on which Advance Ruling Required:
1) Whether GST is applicable to LD in case of
Type 1 i.e. : Operation & Maintenance activities
Type 2 i.e. : Construction of new power plants or renovation of old plants
GST is applicable to liquidated Damages (LD) in both type of cases As LD is treated as consideration by Appellant which is supply under Schedule II entry no. 5(2)(e)of MGST Act.
2) If GST

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

the amount of LD imposed over him as Input Tax Credit subject to satisfying all other conditions?
a) GST on LD is covered under Schedule II entry no 5(2) (e), GST rate will be as per the contract on which LD is imposed.
b)Time of Supply of Services in GST is when any 2 of following conditions are fulfilled;
i. Date of Service invoice raised
ii. Dale of Service performed
iii. Date of payment received Section 13(2) of MGST Act.
c) As above
d) Contractor/Vendor may get input Tax Credit subject to satisfying all other conditions.
04. HEARING
The case was taken up for preliminary hearing on dt.06.02.2018 when Sh. S. S. Gupta, Sh. Karan Awtani, Sh. Ashutosh Shukla (all Chartered Accountants) attended alongwith Sh. Pankaj Sharma, Chief General Manager (Accounts) and Sh. Vijay Chitlange, General Manager (Accounts) and submitted that their Advance Ruling (AR) application is for query covered in section 97(2) of the AR provisions. However, they were informed that their application was

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ted that they would be submitting, latest by dt.08.03.2018, copies of invoices evidencing recovery of liquidated damages. Jurisdictional Officer Sh. S.D. Page also appeared and made written submission.
05. OBERVATTONS
We have gone through the facts of the case. The questions posed are in respect of 'liquidated damages'. We find that the applicant contends that these damages being towards deficiency of services and reduce the original consideration and will not be considered as separate service covered by the term 'Obligation to tolerate an act or a situation'. To understand the appropriateness of this contention, we would have to go through the facts. There is also a sample agreement provided but before that let us revisit the brief introduction as given by the applicant as under –
* Maharashtra State Power Generation Company Limited (Mahagenco) is a State Power Utility engaged in generation of power with objective to make Power available to all at affordable rates.

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

he contract is fixed. When plant construction is completed, the actual time taken for completion of contract is calculated. If there is delay in completing the contract, the assessment regarding party responsible for delay is made. If the delay is on account of contractor, then Liquidated damages (LD) are calculated as per contract terms and levied upon the contractor.
* In accounting, the LD imposed is reduced from the total project cost while capitalising the asset. Because of delay in the execution of work, the cost of project increases on account of Interest During Construction (IDC) and other administrative overheads. In such situation, LD helps in mitigating the impact of higher costs in form of IDC and administrative charges. Moreover, the contract entered into is for the purpose of construction of plant. There is no explicit agreement between the company and the contractor wherein the company is intending to supply service of tolerance of delay. The delay is neither desired b

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

r is desirous that certain ancillary services should be provided by the Contractor, viz. Erection, Testing & Commissioning of Main Plant equipments consisting of Steam Generator, Steam Turbine and Generator, C&I, Electrical equipments and other Auxiliary Equipments for Chandrapur T.P.S. Expansion Project – 2×500 MW and in furtherance of above, the Owner has issued a Letter of Award No. DG/Chandrapur Expn. Proj./MP/Erection & Commg./3415 dated 25.07.2008 and Letter No. DG/CHN 2x500MW./MP/Erection/0452 dated 21.01.09 (Amendment-1) to the Contractor for Erection, Testing & Commissioning of Main Plant equipments consisting of Steam Generator, Steam Turbine and Generator, C&l, Electrical equipments and other Packages for Chandrapur T.P.S. Expansion Project – 2×500 MW for the sum of Rs. 2 ,75,28,20,000.00 (Rupees Two Hundred Seventy Five Crore Twenty Eight Lakh Twenty Thousand only) (hereinafter called “the Contract Price”) which is accepted by the Contractor vide their Letter No. MS-4-08-00

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

s prior to erection of material, insurance, erection, testing and commissioning, final painting and putting into operation of the Main Plant Equipments supplied by BHEL under supply contract vide LOA under ref. 13. The scope of works against this LOA shall also include unloading and handling over of Mandatory Spares to MahaGenco's stores after receipt in good condition & joint verification at site by the contractor and the owner.
2.2 All consumables, paints, chemicals,, equipments, piping and all temporary works required for hydraulic test, boiler light up, alkali boil out, acid cleaning, steam blow off etc. for carrying out erection, testing & commissioning of the unit at site are to be arranged by the Contractor within the scope. The Contractor shall also be responsible for arranging auxiliary steam required during unit commissioning within the scope.
3.0 CONTRACT PRICE
3.1 The contract price for Erection, Testing & Commissioning of Main Plant equipments is Rs. 2784280800.00 (

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

be examined beyond the cut off dates for reasons attributable to the Contractor, for making payments towards price variation, the Owner shall select the indices in the P.V. formula either by restricting their value to contractual cut off date or the actual indices prevailing at that time whichever is lower. In case the contractual period is extended for the reasons attributable to the Owner in such an event the price variation shall be payable on the extended period of contractual cut off dates, based on the prevailing price indices.
8.0 PROJECT COMPLETION SCHEDULE
8.1 The Contractor shall so organize his resources and perform his works as per the Project Completion Schedule enclosed herewith so as to achieve synchronization and Trial Operation of the Unit as below.
 
Period in months from the zero date
 
Unit-1
Unit-2
Unit Synchronization :
38 (Thirty-eight)
41 (Forty-one)
Trial Operation
41 (Forty-one)
44 (Forty-four)
 
9.0 ZERO DATE
9.1 The zero date

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ent schedule / Billing Break-up approved by the Owner. The Contractor should note that financing of this project shall be covered under loan from Rural Electrification Corporation (REC), Mumbai. The Invoices along with the documents listed in the relevant clauses of terms of payment shall be submitted by the Contractor to the General Manager (Gen. Project), Maharashtra State Power Generation Co. Ltd. (MahaGenco) Chandrapur TPS. Expansion Project, Post- Urja Nagar, Chandrapur – 442 404, Dist. Chandrapur for all the payments against this IOA, except for the payment of advance and comprehensive insurance charges.
11.1.2  Service Tax shall be paid on submission of Invoices along with an undertaking from BHEL Unit that the amount of Service Tax claimed in the said Invoice shall be deposited with Government Authorities as per Service Tax Act. M/s. BHEL shall also furnish the certificate on quarterly basis from Head of Finance from the respective Unit certifying that the Service Tax cla

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ng and commissioning of the equipment handling, unloading, storage etc. as per contract.
3.13 (A) Contract Price shall mean the total lump-sum price named in the contract for providing all services as per the scope of the contract including all applicable taxes, duties & insurance charges.
(B) Total Contract Price means the contract price plus the price variations, if any.
3 14 “Contract value” shall mean that part of the contract price which is properly apportionable to the plant or work in question having regard to the state, conditions and topographical location of the plant, the amount of work done and all other relevant circumstances and disregarding any changes that may have occurred since the date of contract in the cost of executing the works.
16.0 DEDUCTIONS FROM TOTAL CONTRACT PRICE
16.1 The Owner shall claim all costs, damages or expenses that the Owner may have paid, for which under the contract the Contractor is liable.
The Owner to the Contractor shall bill all such

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

r to make good the failure, neglect or contravention complained off Should the contactor fail to comply with the notice within 30 (thirty ) days from the date of service thereof, then and m all such cases, the owner shall he at liberty to employ other workmen and forthwith execute such part of the works as the contractor may have neglected to do or. it the owner shall deem fit, it shall be lawful for him, without prejudice to any other right he may have under the contract, to take the works wholly or in part out of the contactor's hand and re-contract w till any other person or persons to complete the works or any part thereof.
The owner shall be entitled to retain and apply any balance which may otherwise be due to the contactor or such part thereof, as may be necessary, to the payment of cost of executing the said part of the works or of completing the works. If the cost of executing the said part of the works or of completing the works thereof as aforesaid shall exceed the bala

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

RECTION, TESTING AND COMMISSIONING
7. 1 The Contractor shall strictly adhere to the Protect completion schedule to achieve the trial operation units 8 & 9 by 41 and 44 months respectively. In case the Contractor fails to achieve successful completion of Trial Operation within specified time period as per the project completion Schedule due to delay on his part, then the Owner shall levy liquidated damages.
7.2 Time Schedules indicated for various activities are for the purpose of monitoring to ensure work completion as per Project Completion Schedule. Only the successful completion of Trial Operation of the unit shall be considered for the purpose of levy of Liquidated Damages.
7.3 The payment by Contractor or deduction by Owner of any sums under the provision of this clause shall not relieve the Contractor from his obligations to complete the works or from his other obligations under the contract.
7.4 The liability of payment of these liquidated damages by the Contractor will be e

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

insurance charges, taxes and duties) along with applicable price variation per week of delay or part thereof subject to the maximum 10% of the contract price for erection, testing and commissioning (excluding insurance charges, taxes and duties) along with applicable price variation.”
7.7 For the purpose of deciding the amount of Liquidated Damages on the erection price, contract price along with the applicable price variation (excluding taxes, duties and insurances charges.) as per contact price adjustment shall be considered.
Further Liquidated Damages for each unit shall be levied separately and for this purpose, price of one unit shall be half of the price of both the units.
13.5 PAYMENT TOWARDS ERECTION, TESTING AND COMMISSIONING
13.5.1  10% (ten percent) advance on the price for Erection, Testing & Commissioning of Equipments alongwith applicable service tax & education cess but excluding insurance charges shall be paid within 30 (thirty) days of fulfillment of the foll

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

uments shall be submitted. ………….
i) Invoice 1 Original + 2 copies
13.5.4  PAYMENT TOWARDS MARINE CUM ERECTION INSURANCE CHARGES
13.6.1  100% payment towards Marine-cum Erection insurance charges alongwith applicable service tax and education cess, shall be released on submission of following documents …………………
i) Invoice 1 Original + 2 copies
A perusal of the above provisions make us observe that the contract price and the liquidated damages are two different aspects. Deduction of one from the other is a mere facilitation towards settlement of the accounts. This manner of giving effect to the obligations under the contract should not be deceptive of the actual intent. We observe so for reasons thus –
1. The agreement says that if the Contractor fails to achieve the trial operation of the unit within the stipulated time period as indicated above from the zero date then the Owner shall levy Liquidated Damages on the contractor @1/2% of the contract pr

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

coverable liability. This is the second event. What we say has been incorporated in the agreement in the words thus – The liability of payment of these liquidated damages by the Contractor will he established once the delay in successful completion of trial operation is established on the part of the Contractor.
3. Both the events have their consequences. The first event calls for the payment of a contract price to the Contractor. The second event calls for payment of liquidated damages to the Owner.
4. The manner employed for recovery of the contract price or the liquidated damages would not define what a contract price or the liquidated damages mean.
5. The deduction from the amount as payable to the Contractor is for the purposes of adjustment of the accounts.
6. Though the situation is so, even if the agreement had clauses regarding deductions form the contract price, we are convinced that we wouldn't have had a different opinion than the one as taken above. Both the contra

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

alue refer to the eventuality of liquidated damages. Contract price is the total lumpsum price plus the price variations. There is no specific indication as to reduction in the contract price due to the levy of liquidated damages.
b. The price variations also have been set out in the agreement thus –
4.0 CONTRACT PRICE ADJUSTMENT / VARIATION
The price for erection, testing & commissioning excluding insurance charges and taxes & duties, shall be subjected to price variation as per the Terms of Bid Specification under ref.l with Base Indices as on March 08. The price variation shall be subjected to a ceiling of (+/-) 20% of the contract price for Erection, Testing & Commissioning excluding taxes & duties and insurance charges.
As can be seen, the price variations to which the contract price would be subjected to makes no reference to the effect of levy of liquidated damages.
c. There is also a clause about deductions from the contract price thus –
16.0 DEDUCTIONS FROM TOT AI CONTRA

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

recovery by way of adjustment from the payments to be made to the Contractor.
d. There is also a clause about Contractor's default thus –
21.0 CONTRACTOR'S DEFAULT
21.1 If the contactor shall neglect to execute the works us defined in the contract with due diligence and expedition or shall refuse or neglect to comply with any reasonable orders given to him in writing by the Engineer in connection with the works or shall contravene the provisions of the contract, the Owner may give a notice in writing to the contractor to make good the failure, neglect or contravention complained off Should the contactor fail to comply with the notice within 30 (thirty) days from the date of service thereof, then and in all such cases, the owner shall be at liberty to employ other workmen and forthwith execute such part of the works as the contractor may have neglected to do or. if the owner shall deem fit, it shall be lawful for him. without prejudice to any other right he may have under th

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

wards advance or payment for execution, testing, commissioning also does not require invoices to be considered taking into consideration the liability towards liquidated damages. The invoices to be prepared are in terms of the contract price. And we see that the bills as submitted for our perusal also do not show a bill being raised after considering liquidated damages. The bills are for work done during a particular period and are accompanied by a Certificate which says in a pointwise manner as to how the amounts have been arrived at. On this Certificate, there are some rough workings as made by the applicant which show calculations involving subtractions, one such subtraction being for liquidated damages. However, if we minutely look at the deductions, it is seen thus –
Invoice as raised by the Contractor
Rough working by the Owner (applicant)
1 Boiler & Aux – Unit-9
For the work done during March'13
As per the Annex Enclosed
375, 29,811
37529810
4174816
41704626
&nbs

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

what would matter is the value for the work done. And once this valuation is properly done and tax liability thereon discharged, whether this value is paid partially or not paid at all would not be a concern from the taxation perspective but a matter between the contracting parties.
The above treatment by both the parties reveals two things –
* It negates the contention that since recovery of Liquidated Damages is a part of the contract, the value of the main supply reduces to the extent of Liquidated Damages deducted by the applicant.
* It confirms the position as brought out in the agreement clauses that recovery of Liquidated Damages is an independent liability.
* The manner of deducting the amount of Liquidated Damages from the amount payable to the Contractor does not alter the valuation of the deliverables or the supplies made under the agreement.
8.  We have to observe that the applicant is not the supplier in terms of the amounts received as contract price or cont

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

esent case, the agreement clauses as reproduced above, the invoice as prepared card the calculations, as reproduced above, as made by the applicant reveal that there are no two opinions between the contracting parties that the value of the supply as received by the applicant does not include the liquidated damages. There are measures identified in the agreement to arrive at the contract value or the invoice value. The words ” price actually paid or payable” in respect of the value of the goods or services supplied do not come into play in the present set of facts of deduction of the amount towards liquidated damages. We have seen above that this deduction does not mean that the price actually paid is less. The income of the applicant is recovered by deducting from the outgoings of the applicant. This would not translate into making the income of the applicant as being the other party's lesser income or the applicant's lesser expenditure. We have seen above that the contract pri

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

he Contractor. Thus, the act of delayed supply has happened. The same is being tolerated by an additional levy in the nature of liquidated damages. The agreement has also provided that the payment by Contractor or deduction by Owner of any sums under the provision of this clause shall not relieve the Contractor from his obligations to complete the works or from his other obligations under the contract. This provision just ensures that the obligations under the contract are fulfilled. The facts are much obvious that the empowerment to levy liquidated damages is for the reason that there has been a delay and the same would be tolerated, but for a price or damages. The impugned income though presented in the form of a deduction from the payments to be made to the Contractor is the income of the applicant and would be a supply of 'service' by the applicant in terms of clause (e) of para 5 of Schedule II appended to the GST Act.
10. The applicant has referred to a few case laws and

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

h as made by the Contractor. In fact in the present case, the levy of liquidated damages is specifically identified as an independent levy. We have seen that the Contract Price Variation clause in the impugned agreement, does not provide for variation on account of liquidated damages. And above all, we have seen the intent as being reflected in the treatment of the parties as not to alter the value of the work done and the tax liability on such value while making deductions therefrom. The reliance on case laws is, therefore, not helpful to the applicant. The facts of the instant case before us being distinct, we would refrain from discussing the other points in support of the contention.
Having seen as above, we refer to the questions as posed for our decision.
Question 1
Whether GST is applicable on Liquidated Damages in case of
Type 1 i.e. Operation & Maintenance activities
Type 2 i.e. Construction of new power plants or renovation of old plants
Or is applicable in both cases?

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

levy of liquidated damages would be covered by clause (e) of para 5 of Schedule II appended to the GST Act.
To answer the question as regards the schedule entry and the tax rate applicable, we find that there is no specific schedule entry in the Notification no.11/2017 – Central / State Tax (Rate) [as amended from time to time] for taxable services and the Notification no.12/2017 – Central / State Tax (Rate) [as amended from time to time] for services exempt from GST. A reference to the Annexure about Scheme of Classification of Services as appended to the Notification no.11/2017 – Central / State Tax (Rate) [as amended from time to time] reveals thus –
S. No.
Chapter, Section, Heading, Group
Service Code (Tariff)
Service Description
700
Heading 9997
 
Other services
716
Group 99979
 
Other miscellaneous services
720
 
999794
Agreeing to tolerate an act
722
 
999799
Other services nowhere else classified
In view of the above, following schedu

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ails to achieve the trial operation of the unit within the stipulated time period as indicated above from the zero date then the Owner shall levy Liquidated Damages on the contractor @1/2% of the contract price for Erection, Testing & Commissioning along with applicable price variation price per week of delay or part thereof subject to a maximum of 10% of the price for Erection, Testing & Commissioning along with applicable price variation. For the purpose of levy of liquidated damages, the contract price for Erection, Testing & Commissioning excluding Insurance charges and taxes & duties and the same for one unit shall be half of the total price.
* Section 3 – Special Conditions of Contract
7.0 LIQUIDATED DAMAGES FOR DELAY IN ERECTION, TESTING AND COMMISSIONING
7. 1 The Contractor shall strictly adhere to the Protect completion schedule to achieve the trial operation units 8 & 9 by 41 and 44 months respectively. In case the Contractor fails to achieve successful completion of Tria

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

es.
7.5 Since the Liquidated damages are limited and the same cannot compensate the consequential loss of the Owner due to delay on the part of the Contractor, the Owner reserves the right to get the work done at the risk and cost of the Contractor. in case delay on the part of the Contractor has been established after giving notice to the Contractor. as may be deemed fit in the interest of completing the balance works.
7.6 If the contractor fails to achieve the Trial Operation of the unit within the time period specified in the Project Completion Schedule due to reasons attributable to him then the owner shall levy Liquidated damages on the Contractor @1/2% of the contract price for erection, testing and commissioning (excluding insurance charges, taxes and duties) along with applicable price variation per week of delay or part thereof subject to the maximum 10% of the contract price for erection, testing and commissioning (excluding insurance charges, taxes and duties) along with a

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

of delay or to the period falling after GST roll-out? In case when GST is to be imposed for period after date of GST rollout but due to maximum capping of LD, the amount of LD is calculated at given percentage instead of being period-based, then how GST needs to be levied.
The question is based on some incorrect presumption owing to which the applicant seems to have adopted some method of deduction of liquidated damages from the payments to be made to the contractor. We are afraid that no such strategy of deducting or of capping can be inferred from the agreement clauses. We would be constrained to restrict the answer to this question in terms of only the agreement placed before us. Sub-section (1) of section 13 of the GST Act provides that the liability to pay tax on services shall arise at the time of supply. If the Contractor fails to achieve the Trial Operation of the unit within a specified time period which falls under the GST regime then levy of liquidated damages would be attr

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ows:
ORDER
(under section 98 of the Central Goods and Services Tax Act, 2017 and the Maharashtra Goods and Services Tax Act, 2017)
 
NO. GST-ARA-15/2017-18/B-30
Mumbai dt.  08/05/2018
For reasons as discussed in the body of the order, the questions are answered, as under, in terms of the agreement between Maharashtra State Power Generation Company Limited (Owner) and Bharat Heavy Electricals Limited (Contractor) for Erection & Commissioning of Main Plant Package at Chandrapur T.P.S. Expansion Project 2 x 500 MW –
Q.1 Whether GST is applicable on Liquidated Damages in case of
Type 1 i.e. Operation & Maintenance activities
Type 2 i.e. Construction of new power plants or renovation of old plants
Or is applicable in both cases?
A.1 In terms of the aforesaid agreement, GST would be applicable on the Liquidated Damages.
Q.2 If GST is applicable, kindly clarify the following related aspects also –
Q.2(a) Whether the GST on Liquidated Damages is covered under Schedule

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ome part of delay has occurred before GST roll-out and some part of delay has occurred after GST roll-out, whether GST will be applicable to the Liquidated Damages imposed for entire period of delay or to the period falling after GST roll-out? In case when GST is to be imposed for period after date of GST rollout but due to maximum capping of LD, the amount of LD is calculated at given percentage instead of being period-based, then how GST needs to be levied.
A.2(b) Sub-section (1) of section 13 of the GST Act provides that the liability to pay tax on services shall arise at the time of supply. In view thereof, as discussed in the answer to the Q.2(b), the agreement clauses would have to be referred to. Since no precise facts are before us, the section 14 of the GST Act would have to be referred to by the applicant.
Q.2(d) Whether the contractor/vendor will be able to utilize the amount of LD imposed over him as Input Tax Credit subject to satisfying all other conditions?
A.2(d) The

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Appointment of Appellate Authority under DGST Act, 2017

Appointment of Appellate Authority under DGST Act, 2017
F. No.(3)/HR/DGST/2018/5220-29 Dated:- 8-5-2018 Delhi SGST
GST – States
Delhi SGST
Delhi SGST
GOVERNMENT OF NATIONAL CAPITAL TERRITORY OF DELHI
DEPARTMENT OF TRADE AND TAXES
(HUMAN RESOURCE BRANCH)
VYAPAR BHAWAN, I.P. ESTATE, NEW DELHI-110002
NOTIFICATION
F. No.(3)/HR/DGST/2018/5220-29
Dated: 08/05/2018
Appointment of Appellate Authority under DGST Act, 2017
In exercise of the power conferred upon me by sub-section (1

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

In Re : Dinesh Kumar Agrawal

In Re : Dinesh Kumar Agrawal
GST
2018 (6) TMI 466 – AUTHORITY FOR ADVANCE RULINGS, ANDHRA PRADESH – 2018 (13) G. S. T. L. 474 (A. A. R. – GST)
AUTHORITY FOR ADVANCE RULINGS, ANDHRA PRADESH – AAR
Dated:- 8-5-2018
Ruling No. AAR/AP/3O(GST)/2018 In Application No. AAR/05(GST)/2018
GST
MR. J. V. M. SARMA, JOINT COMMISSIONER (STATE TAXES), AUTHORITY ADVANCE RULING, ANDHRA PRADESH AND MR AMARESH KUMAR, JOINT COMMISSIONER (CENTRAL TAXES), AUTHORITY FOR ADVANCE RULING, ANDHRA PRADESH
For The Present Applicant : Applicant himself attended
RULING
Mr. Dinesh Kumar Agrawal, R/o #501, ACME Regency, 5m floor, SV Road, Vile Parle (West), Mumbai, Maharashtra (hereinafter also referred as an applicant), is an unregistered taxpayer, is engaged in erection and supply of solar power generating system by making an agreement with his customers, has filed an application on 09,h February 2018. Vide acknowledgement number VPG736416, for seeking advance ruling for the tax rates applicab

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ty.
1. The Issues raised by the applicant is as follows.,
Issue No. 1 Whether supply of solar power plant under 'Turnkey EPC Contract' is supply of 'solar power generating system' under Entry 234 of Schedule I of the Notification No. 1/2017- Integrated Tax (Rate), Entry 234 of Schedule I of the Notification No. 1/2017- Central Tax (Rate) both dated 28 June 2017 and Entry 234 of Schedule I of the Notification No. 1/2017-State Tax (Rate) dated 29 June 2017?
Issue No. 2 Whether supply of solar power plant under 'Other EPC Contract' is supply of 'solar power generating system' under Entry 234 of Schedule I of the Notification No. 1/2017- Integrated Tax (Rate), Entry 234 of Schedule I of the Notification No. 1/2017- Central Tax (Rate) both dated 28 June 2017 and Entry 234 of Schedule I of the Notification No. 1/2017- State Tax (Rate) dated 29 June 2017?
Issue No.3 Whether supply of solar power plant under 'Supply Contract' is supply of 'solar power generating system' under Entry 234

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

is supply of 'solar power generating system' under Entry 234 of Schedule I of the Notification No. 1/2017- Integrated Tax (Rate), Entry 234 of Schedule I of the Notification No. 1/2017- Central Tax (Rate) both dated 28 June 2017 and Entry 234 of Schedule I of the Notification No. 1/2017- State Tax (Rate) dated 29 June 2017?
Issue No.6 If the Clarification to Issue No. 5 is negative, what would be nature of supply i.e. composite supply or mixed supply?
Issue No.7 Whether contract for assembly, erection, and commissioning of the plant undertaken by the Applicant under a separate contract would be a service contract liable to be taxed under Service heading 9954?
Issue No.8 Whether the time of supply of power plant shall be determined under Section 31 (4) of the CGST Act/SGST Act read with Section 12(2) thereof?
The Issues raised by the applicant is fit to pronounce advance ruling as they falls ambit of the Section 97(2) (a), (b) and (c), they are as given under
(a) Classification

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

m etc.
(ii) Designing, procurement and supply of all equipment/components for the power plant
(iii) Assembly, erection, and commissioning
(iv) Operations and Maintenance of the plant between 2 to 15 years
In Other EPC Contract, the Applicant is required undertake all activities of turnkey projects except civil work. The scope of work typically involves:
(i) Designing, procurement and supply of all equipment/components for the || power plant
(ii) Assembly, erection, and commissioning
In Supply Contract, the Applicant is required to supply the power plant on complete knocked down condition in piecemeal at project site. Customer engages a third party contractor or the Applicant for assembly, erection, and commissioning of the plant under a separate contract.
In Balance of Plant Supply Contract, the Applicant is required to supply goods and services stated above, except solar panels. Solar panels procured by the customer are made available by the customer to the Applicant for

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

& erection
ii. Supply of nut, bolts, fasteners and other miscellaneous materials
e. Test & Commissioning
B. Equipment and components are delivered at project site and stored at the risk of the Applicant
C. Ownership is transferred on successful commissioning of the plant
D. Payment is as per milestone or monthly depending on the % of goods delivered at site
E. Full payment is released on successful commissioning of the plant with stipulated power generation.
F. Cost:
a. In the case of Ground Base Solar Project: 20% Civil & Erection & 80% Supply. Roof Top Base Solar Project: 10% Civil & Erection & 90% Supply.
For Issue number 2, the statement of facts are as follows…
The scope of supply includes:
a. Detailed designing of power project
b. Procurement and supply at project site
i. Solar photovoltaic modules/panels/array
ii. Panel mounting structure
iii. Solar tracker
iv. Meteorological equipment
v. Cables
vi. Combiner box
vii. Solar power conditioning unit

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

s
vi. Combiner box
vii. Solar power conditioning unit
viii. Inverter
ix. Isolator
x. Transformer
xi. Switchbox
xii. Conductor
xiii. Battery
xiv. Transmission tower
xv. Steel/plastic tubes & pipes
xvi. SCADA Software
b. Equipment and components are delivered at project site and risk is transferred to the customer
c. Payment is as per milestone or monthly depending on the % of goods delivered at site
d. Full payment is released on successful commissioning of the plant with stipulated power generation.
A. Scope of Erection Contract includes:
a. Assembly & erection
i. Assembly & erection
ii. Supply of nut, bolts, fasteners and other miscellaneous materials
b. Test & Commissioning
B. Risk of Equipment and components are acquired by the Applicant during erection till successful handover of the plant to the customer
C. Payment is as per milestone or monthly depending on the % of goods delivered at site
D. Full payment is released on successful commissioni

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ent is as per milestone or monthly depending on the % of goods delivered at site. Full payment is released on successful commissioning of the plant with stipulated power generation.
For Issue number 5, the statement of facts is as follows….
A. The scope of supply includes:
a. Civil works
i. leveling of ground
ii. Wall boundary
iii. internal roads
iv. concrete foundations for mounting of panel mounting structures
v. digging ditch for underground cabling
vi. Concrete flooring for inverter/transformer/battery pack,
vii. Control room etc.
b. Detailed designing of power project
c. Procurement and supply at project site
i. Panel mounting structure
ii. Solar tracker
iii. Meteorological equipment
iv. Cables
v. Combiner box
vi. Solar power conditioning unit
vii. Isolator
viii. Transformer
ix. Switchbox
ix. Conductor
xi. Battery
xii. Transmission tower
xiii. Steel/plastic tubes & pipes
xiv. Pre-fabricated shelter
xv. SCADA Software
d. Assembl

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

ing ditch for underground cabling
vi. Concrete flooring for inverter/transformer/battery pack,
vii. Building of control room etc.
b. Assembly and Erection
i. Assembly & erection
ii. Supply of nut, bolts, fasteners and other miscellaneous materials
iii. Test & Commissioning
A. Risk of Equipment and components are acquired by the Applicant during erection successful handover of the plant to the customer.
B. Payment is as per milestone or monthly depending on the % of goods delivered at site Full payment is released on successful commissioning of the plant with stipulated power generation.
And for Issue number 8, the statement of facts is as follows…
The contract stipulated successive payment against successive statements depending on the milestone stipulated in the contract.
On analyzing the Issues, with respect to the CGST/SGST Act, rules, and notifications released from time to time, it is to note Entry number 234 of Schedule I ( which are taxable @ 2.5% ) of notifica

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

1 (4) reads “In case of continuous supply of goods, where successive statements of accounts or successive payments are involved, the invoice shall be issued before or at the time each such statement is issued or, as the case may be, each such payment is received”.
(IV) section 12(2, reads “The time of supply of goods shall be the earlier of the following dates,” namely:-
(a) the date of issue of invoice by the supplier or the last date on which he is required, under sub-section (1) of section 31, to issue the invoice with respect to the supply; or
(b) the date on which the supplier receives the payment with respect to the supply:
Provided that where the supplier of taxable goods receives an amount up to one thousand rupees in excess of the amount indicated in the tax invoice, the time of supply to the extent of such excess amount shall, at the option of the said supplier, be the date of issue of invoice in respect of such excess amount.
On plain reading of the above facts along

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

y the applicant, the scope of work in respect of “Turn key EPC Contract” and “Other EPC Contract” includes civil works, procurement of goods and erection and commissioning. Accordingly, “Turnkey EPC Contracts” and “Other EPC Contracts” are not getting covered under supply of 'solar power generating system' under Entry 234 of Schedule I of the Notification No. 1/2017- Integrated Tax (Rate), Entry 234 of Schedule I of the Notification No. 1/2017- Central Tax (Rate) both dated 28 June 2017 and Entry 234 of Schedule I of the Notification No. 1/2017- State Tax (Rate) dated 29 June 2017.
Issue No.3: Whether supply of solar power plant under 'Supply Contract' is supply of 'solar power generating system' under Entry 234 of Schedule I of the Notification No. 1/2017- Integrated Tax (Rate), Entry 234 of Schedule I of the Notification No. 1/2017-intergrated Tax (Rate), Entry 234 of Schedule I of the Notification 1/2017-Central Tax (Rate) both dated 28 June 2017 and Entry 234 of Schedule I of the

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

-Central tax (Rate), dated 28th June, 2017. And the supply of service attracts at the rate specified thereon in Notification No. 11/2017 -Central tax (Rate).
Issue No.4: Whether supply of solar power plant under 'Supply Contract' is supply of 'solar power generating system' under Entry 234 of Schedule I of the Notification No. 1/2017- Integrated Tax (Rate), Entry 234 of Schedule I of the Notification No. 1/2017- Central Tax (Rate) both dated 28 June 2017 and Entry 234 of Schedule I of the Notification No. 1/2017- State Tax (Rate) dated 29 June 2017 where the assembly, erection, and ' commissioning of the solar power plant is undertaken by a third party contractor?
Ruling : In this scenario, the goods are supplied by one contractor, and the services were supplied by the other contractor. Therefore the rate of tax applicable for supply of goods as long as it satisfies the condition of being ” device and parts” of the solar power generating system attracts 5% rate of tax as per Entry 23

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

per the Entry 25 of 25 (Heading 9987) of Notification No. 11/2017 – Central Tax (Rate), dated : 28th June 2017, and attracts 18% rate of tax.
Issue No.6: If the Clarification to Issue No. 5 is negative, what would be nature of supply i.e. composite supply or mixed supply?
Ruling : Ruling covered under clarification in issue number 5 (five)
Issue No.7: Whether contract for assembly, erection, and commissioning of the plant undertaken by the Applicant under a separate contract would be a service contract liable to be taxed under Service heading 9954?
Ruling : The referred contract doesn't fall under the ambit of SAC 9954, but falls under the Entry 25 of 25 (Heading 9987) of Notification No.11/2017 -Central Tax (Rate), dated: 28th June 2017, and attracts 18% rate of tax.
Issue No.8 Whether the time of supply of power plant shall be determined under Section 31 (4) of the CGST Act/SGST Act read with Section 12(2) thereof?
Ruling:          &

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

In Re : M/s. National Dairy Development Board

In Re : M/s. National Dairy Development Board
GST
2018 (7) TMI 76 – AUTHORITY FOR ADVANCE RULING, GUJARAT – 2018 (14) G. S. T. L. 483 (A. A. R. – GST), [2018] 2 GSTL (AAR) 84 (AAR)
AUTHORITY FOR ADVANCE RULING, GUJARAT – AAR
Dated:- 8-5-2018
ADVANCE RULING NO. GUJ/GAAR/RULING/2018/11 (IN APPLICATION NO. Advance Ruling/SGST&CGST/2017-18/AR/22)
GST
Mr. R. B. Mankodi, Member And Mr. G. C. Jain, Member
For The Applicant : Shri Hardik Shah, CA
RULING
The applicant, NDDB, is a statutory body constituted by an Act of Parliament, namely the National Dairy Development Board Act, 1987 (NDDB Act); the objectives of NDDB include promoting dairy and other agriculture based industries; and the activities undertaken by NDDB, to fulfill its objectives, include providing technical, financial as well as managerial assistance.
1.1 The applicant submitted that the NDDB Act also empowers them to transfer the whole or any part of its managerial, technical or other functions in rel

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

and developing dairying in the respective states; that the state governments have entrusted NDDB to run the management, appoint key managerial persons and provide end to end services which ultimately would help the Unions in developing.
1.3 It is further stated that as per the agreements made by them with these state governments on the matter, the applicant undertake following end to end activities as if they are owning and running Unions-
(i) Taking over management of Unions and deputation of key managerial persons including managing director
(ii) Preparation of business plans and implementation of the same
(iii) Decide on procurement and distribution channels and preparation of policies thereof
(iv) Determine the pricing policies for sale of products and usage of brands owned by Unions
(v) Borrowing of funds as and when required
(vi) Taking relevant decisions in order to achieve sustainable growth for Unions.
1.4 They further submitted that the applicant provides servi

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

nce of business would be contemplated as supply of goods or service; that in order to be supply, it is essential to understand whether NDDB and Unions would be considered as related persons.
1.7 The applicant then by referring to the Section 15 of CGST Act and Rule 28 of CGST Rules, submitted that the moot question arises in the matter is that whether the applicant and Unions can be considered as related parties attracting open market valuation only because of control exercised over Unions on the basis of agreements entered into with the state governments which means that the privity of contract is between the applicant and the state governments; that the state governments have instructed to manage all operations and performing all activities without consideration; that it is the duty of the state governments to develop the dairy industry in the state; that in such scenario, the benefit of handing over the management of Unions to experts would accrue the state governments only; that t

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

never be established between the service provider and the beneficiaries. The applicant then submitted that, in absence of any kind of relationship between NDDB and Unions in the given contract, the question of valuation of services at open market value does not arise at all and the zero value would be treated as sole consideration for supply, subject to tax.
1.11 The applicant further submitted that irrespective of their above submissions, even if it is assumed that there exist relationship between the applicant and Unions as a reason of control of the applicant over Unions, the price for services is not influenced because of relationship; that it is at the instance of the state governments, they provide services at free of cost; that it is an obligation of state government for revival and development of dairy industries and they are insisting the applicant to not charge any sum; that such kind of reason or moral support provide by them cannot be equated with normal related party tran

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

em or any beneficial interest.
1.13 The applicant further stated that it is logically inappropriate that when the applicant does not charge anything and the arrangement is undertaken at transaction value or for price which is sole consideration, then also by reason of control, the applicant would be required to value the services and pay hefty taxes in absence of any kind of extra commercial benefit.
1.14 On the basis of above facts and submissions, the applicant has sought ruling on following points-
(i) By virtue of tripartite agreement between NDDB, State Government & Unions, whether the arrangement between NDDB and Unions would be considered as supply between 'related persons' in accordance with Schedule 1 of the Central Goods & Service Tax Act, 2017?
(ii) Assuming answer to above point is affirmative, whether the applicant would be required to determine value of activities undertaken by them in accordance with Section 15(5) of CGST Act, 2017 read with Rule 28 of the CGST Rul

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

rsons as specified in section 25, when made in the course or furtherance of business.
4. Provisions of Section 15 of CGST Act, 2017 provides for valuation of taxable supply of goods or services or both. Section 15 of the CGST Act lays down the valuation aspects under GST which explained the value of taxable supply of goods or services or both on which tax is payable. It states that the value of supply of goods and services shall be the 'transaction value' that is the price actually paid or payable for the said supply, where the supplier and the recipient are not related and price is the sole consideration for the supply. Section 15(5) of CSGT Act specify the following situations wherein two persons could be deemed to be 'related persons'
1. Such persons are officers or directors of one another's businesses;
2. Such persons are legally recognized partners in business;
3. Such persons are employer and employee;
4. Any person directly or indirectly owns, controls or holds twe

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

tween the State of Assam and NDDB, made with a view to revive WAMUL, a decision is found to have been taken to hand over the management of WAMUL to NDDB under some terms and conditions specified therein. On perusal of this agreement, NDDB would manage the WAMUL as Administrator by way of implementing suitable business plan for WAMUL, marketing the milk and milk products of WAMUL, deploying suitable man power in WAMUL etc.
7 By the agreement dated 1st March, 2014, between the State of Jharkhand and NDDB, made with the purpose of revitalize the JMU, it was decided to handover the management of JMU to NDDB under the specified terms and conditions therein. As per these terms and conditions, it is seen that NDDB would take over the management of the JMU along with all the assets and manage it as Administrator; that NDDB would prepare planning for developing the JMU and implement it; that NDDB would deploy suitable personnel to key management of JMU; NDDB would work out and implement busine

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

Shree Narmada Khand Udyog, Sahakari Mandli Ltd. Versus Commissioner (Appeals), GST & Central Excise – Vapi

Shree Narmada Khand Udyog, Sahakari Mandli Ltd. Versus Commissioner (Appeals), GST & Central Excise – Vapi
Central Excise
2018 (8) TMI 1075 – CESTAT AHMEDABAD – TMI
CESTAT AHMEDABAD – AT
Dated:- 8-5-2018
Appeal No: E/10352/2018-SM – A/11452/2018
Central Excise
Dr. D. M. Misra, Member (Judicial)
For Appellant (s): Shri Rohit Lalwani, Advocate
For Respondent (s): Shri L. Patra, AR
ORDER
Per: Dr. D.M. Misra
Heard both sides.
2. This is an appeal filed against the order-in-appeal No. VAD-EXCUS-002-APP-346-2017-18 dtd. 25.08.2017 passed by the Commissioner (Appeals), GST & Central Excise-Vapi.
3. The brief facts of the case are that the appellant are engaged in the manufacture of Sugar & Molasses falling under Chapter sub-heading No. 1701 & 1703 of the CETA, 1985. During the course of manufacture of Sugar and Molasses, the by-product, namely, “Bagasse” emerges. Since, the appellant had availed Cenvat credit on various inputs, 6% of the value of the said exempt

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

s contention that even though after amendment to said Rule 6 of CCR, 2004, the process of manufacture remains the same and it emerges as a waste/by-product, only and inevitable during the course of manufacture of Sugar and Molasses. He submits that the ratio laid down by the Hon'ble Supreme Court in the case of M/s Union of India vs. M/s DSCL Sugar Ltd – 2015-TIOL-240-SC-CX is squarely applicable to the facts of the present case.
4. Ld. AR for the Revenue reiterated the findings of the Ld. Commissioner (Appeals).
5. I find that the department has dropped the demand on the by-product “Bagasse” for the period prior to 01.03.2015. However, on insertion of explanation I to Rule 6 of CCR, 2004 by virtue of Notification No. 6/2015-CE(NT) dt. 1.3.2015 a view was taken by the department that bagasse being not an excisable goods and cleared from the factory, against consideration, therefore, would come within the scope of Rule 6 of the CCR, 2004. The said provision, reads as follows:-
“Expla

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

amended definition of 'excisable goods' and 'manufacture', have been considered by the Hon'ble Supreme Court in DSCL Sugar Ltd's case (supra). Their Lordships observed as follows:-
“10. In the present case it could not be pointed out as to whether any process in respect of Bagasse has been specified either in the Section or in the Chapter notice. In the absence thereof this deeming provision cannot be attracted. Otherwise, it is not in dispute that Bagasse is only an agricultural waste and residue, which itself is not the result of any process. Therefore, it cannot be treated as falling within the definition of Section 2(f) of the Act and the absence of manufacture, there cannot be any excise duty.
11. Since if is not a manufacture, obviously Rule 6 of the Cenvat Rules, 2004, shall have no application as rightly held by the High Court.”
7. Following the aforesaid ratio, I do not have any hesitation to hold that even after amendment to Rule 6 of CCR, 2004, 'bagasse' which emerges a

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

NUMBERING OF INVOICES.

NUMBERING OF INVOICES.
Query (Issue) Started By: – kollengode venkitaraman Dated:- 7-5-2018 Last Reply Date:- 8-5-2018 Goods and Services Tax – GST
Got 5 Replies
GST
RULE 48(b) OF THE CGST RULES DEALING WITH INVOICE NUMBERING ENDS AS FOLLOWS"UNIQUE FOR A FINANCIAL YEAR" WHAT DOES IT MEAN? CAN WE USE SL.NO.1TO 5000 IN FY 2017-18 AND AGAIN START WITH SL NO. 1 IN 2018-19?
Reply By Ganeshan Kalyani:
The Reply:
You cannot start from one again. The number should be unique for

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

GSTN to rope in private entities for tax payer profiling, fraud analytics

GSTN to rope in private entities for tax payer profiling, fraud analytics
GST
Dated:- 7-5-2018

New Delhi, May 7 (PTI) GST Network has invited bids from private entities for "360-degree" profiling of taxpayers for early detection of fraud as it seeks to transform into an end-to-end platform for checking GST evasion, from being just a tax collection portal.
The analytics company to be roped in will have the mandate for designing and developing a Fraud Analytics System.
GST Network has however barred Infosys from bidding for the project to avoid conflict of interest.
The system will take about an year to be operational and leverage existing data pertaining to GST registration, return filing and e-way bill, along with

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

t; said the RFP.
It would also establish taxpayer's risk profile by analysing information on purchasers and sellers as part of returns data, whether the taxpayer deals with sensitive or evasion prone commodities, history of the owner of the company as well as rapid change of promoters, among others.
The company, to be appointed for 6 years, would also be required to suggest ways to prevent revenue leakages and forecast revenue growth and other econometric analysis for policy formation.
It can also suggest changes in laws, rules/ procedures based on fraud detection to plug loopholes and identify material/evidences which may be shared with tax authorities for prosecution of fraudulent taxpayers.
To ensure that there is no conflict of

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =

banks, Ministry of Corporate Affairs, Shops and Establishments Department, other Government and non-government agencies etc. which will be integrated with the GST fraud analytics system," it added.
To ensure full confidentiality of data, GSTN has mandated that the eligible bidder would have to ensure a separate section within their office premises for undertaking the fraud analytics project.
GSTN may also place one or two of its employee there for monitoring.
"GSTN may, in case required, provide desktops and laptops for day-to-day operations for carrying out fraud analytics," said the RFP.
Besides, the people involved in the project would not be allowed to "carry any storage device such as USB sticks etc. to GSTN pre

= = = = = = = =

Plain text (Extract) only
For full text:-Visit the Source

= = = = = = = =